Energy Generation, Grid Access, and the Renewable Energy Transition
The interconnection queue represents the backlog of power generation and storage projects seeking access to the electrical grid. As of the end of 2024, approximately 10,300 projects representing 2,300 gigawatts of capacity were actively awaiting interconnection approval in the United States. This queue has become a critical bottleneck for renewable energy deployment, with the median time from initial interconnection request to commercial operation rising from less than two years in the 2000s to more than four years for projects built in recent years. Solar energy dominates the queue at 956 gigawatts of capacity, followed by energy storage at 890 gigawatts and wind at 271 gigawatts. The interconnection queue now contains more than twice the total installed capacity of the entire existing United States power plant fleet, creating unprecedented challenges for grid operators and renewable energy developers. Federal Energy Regulatory Commission reforms issued in 2023 and 2024, including Order 2023 and Order 1920, have begun to address the most egregious delays and cost barriers. However, the fundamental tension between renewable energy development requirements and grid modernization capacity persists. Without substantial acceleration of both interconnection reforms and transmission system expansion, the United States risks failing to meet its energy transition objectives and losing competitive advantage in clean energy technology and manufacturing.
Detailed Findings
The Interconnection Queue: Scale and Composition
As of the end of 2024, the United States interconnection queue contained approximately 10,300 projects representing 2,300 gigawatts of generation and storage capacity actively seeking grid access. This capacity exceeds twice the total installed capacity of the existing power plant fleet. Within the active queue, solar energy projects comprise the largest share at 956 gigawatts, followed by energy storage resources at 890 gigawatts and wind generation at 271 gigawatts. Natural gas projects represent 136 gigawatts of active queue capacity, reflecting changing investment patterns in a period of increased renewable energy development. The composition of the queue reflects both federal renewable energy incentives, particularly the Inflation Reduction Act, and long-term policy commitments to decarbonization at federal and state levels.
The interconnection queue data reveals substantial regional variation. The largest backlog exists in the Pennsylvania, Jersey, Maryland Interconnection, a wholesale electricity market serving multiple eastern United States. The Electricity Reliability Council of Texas, the independent system operator serving Texas, experienced a 300 percent increase in large load interconnection requests in 2024. This regional variation reflects both local renewable energy potential and differences in regional interconnection procedures and standards.
Historical Queue Trends and Withdrawal Patterns
The interconnection queue has experienced dramatic growth over the past decade. A critical finding emerges from analysis of long-term project outcomes: only 13 percent of capacity that submitted interconnection requests between 2000 and 2019 had reached commercial operation by the end of 2024. Seventy-seven percent of that historical capacity had been withdrawn from the queue, and 10 percent remained active. This withdrawal rate demonstrates that extended interconnection timelines impose real economic barriers to project development.
In 2024, the queue declined by 12 percent in total active volume compared to 2023, driven by high withdrawal rates and fewer new interconnection requests. Solar interconnection requests declined by 47 percent compared to 2023, while energy storage requests fell by 32 percent. These declines reflect broader uncertainties in the renewable energy investment landscape, including elevated interest rates, tariff policy changes, local permitting challenges, and political uncertainty regarding federal energy policy. The patterns demonstrate that interconnection delays and costs directly affect capital deployment decisions by renewable energy developers.
Time from Interconnection Request to Commercial Operation
The timeline for interconnection approval and grid connection has deteriorated significantly. Projects built in the 2000 to 2007 period spent less than two years on average from initial interconnection request to commercial operation. By contrast, projects built in the 2018 to 2024 period required more than four years, representing a doubling of the interconnection timeline. The median queue time has extended to eight years or longer in certain restructured electricity markets, particularly the Pennsylvania, Jersey, Maryland Interconnection. This extended timeline creates substantial challenges for renewable energy development:
Elevated capital costs accrue during extended queue periods, reducing project economic viability, particularly for energy storage resources sensitive to changing interest rates and power market economics. Regulatory and policy environments may shift during extended interconnection processes, creating investment uncertainty. Supply chain lead times for renewable generation equipment may exceed interconnection queue wait times, requiring developers to carry inventory costs or defer project construction. Developer confidence in grid access commitments weakens over extended periods, leading to higher risk premiums and capital costs.
Federal Energy Regulatory Commission Order 2023: Interconnection Reform
On July 28, 2023, the Federal Energy Regulatory Commission issued Order 2023 to reform the procedures and agreements that electricity transmission providers use to integrate new generating facilities into the transmission system. The order represents the most significant federal interconnection reform in two decades. Key provisions include:
Cluster Study Process: The order eliminates the first-come, first-served serial interconnection approach in favor of a first-ready, first-served cluster approach. Under the cluster process, transmission providers group projects into cycles and conduct interconnection studies simultaneously for all projects in a cluster. This approach reduces the sequential delay inherent in serial study processes.
Technological Integration: The order requires transmission providers to evaluate alternative transmission technologies in interconnection studies, including static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, and tower lifting. These technologies can defer or eliminate network upgrades required for interconnection.
Co-Location Provisions: Transmission providers must allow multiple projects to co-locate on a shared site behind a single point of interconnection and share a single interconnection request. This provision particularly benefits solar and energy storage developers seeking to deploy multiple resources at the same location.
Affected System Studies: The order establishes consistency and transparency requirements for affected system studies, which analyze impacts on adjacent transmission systems. Pro forma agreements and firm deadlines for affected system study completion reduce delays and disputes.
Higher Interconnection Readiness Requirements: The order increases interconnection readiness requirements, including higher interconnection deposit amounts and commercial operation milestones. These provisions reduce speculative queue positions and improve project commitment.
Firm Study Deadlines and Penalties: The order imposes firm deadlines for transmission provider completion of interconnection studies, with delay penalties distributed to interconnection customers on a pro-rata basis. This provision creates direct financial incentives for timely study completion.
Federal Energy Regulatory Commission Order 1920: Transmission Planning and Cost Allocation
On May 13, 2024, the Federal Energy Regulatory Commission issued Order 1920, establishing new requirements for regional transmission planning and cost allocation. The final rule became effective on August 12, 2024. This order complements Order 2023 by addressing transmission system adequacy and cost responsibility.
Key provisions include:
Long-Range Transmission Planning: Transmission providers must plan transmission systems for at least 20 years forward and conduct such planning at least once every five years. This extended planning horizon addresses long-term renewable energy integration and peak demand management.
Expanded Planning Factors: Planning processes must explicitly incorporate federal and state laws and regulations, integrated resource plans, fuel costs, existing plant retirements, interconnection requests and withdrawals, and stated policy goals. This requirement ensures that transmission planning incorporates the full scope of factors affecting long-term energy system evolution.
Cost Allocation Transparency: Transmission providers must clearly allocate costs for network upgrades required to accommodate interconnection requests. The rule provides mechanisms for state entities and interconnection customers to voluntarily fund portions of transmission upgrades that otherwise would not meet the transmission provider selection criteria, potentially enabling additional projects to proceed.
Completely Firm Timeline Standards: Transmission providers must complete 68 percent of interconnection studies on time. One thousand four hundred thirty-nine interconnection studies were completed late in 2022, representing 68 percent of all studies completed that year. Order 1920 establishes penalties for late study completion, creating direct financial incentives for timely processing.
Interconnection Costs and Economic Impacts
Interconnection costs have escalated significantly in recent years. Transmission interconnection costs reported between 2019 and 2023 were 44 percent greater than during the preceding five years. Within specific regional transmission organizations, the increases have been more severe: interconnection costs doubled for both the Pennsylvania, Jersey, Maryland Interconnection and the Midwest Independent System Operator in recent years.
Energy storage projects face particularly acute cost barriers. Interconnection costs for storage projects in the Pennsylvania, Jersey, Maryland Interconnection queue averaged $335 per kilowatt from 2017 to 2022, compared with $24 per kilowatt for natural gas projects. This cost differential reflects network upgrade requirements driven by the different operational characteristics of storage resources compared with conventional generation. Most proposed storage projects never reach commercial operation, with research indicating that long interconnection delays and grid upgrade costs render projects uneconomic.
The economic impact extends beyond direct interconnection costs. Extended queue times increase developer carrying costs, reduce project returns on investment, and raise the risk premium required for capital deployment. These factors disproportionately affect renewable energy and energy storage projects, which typically carry lower absolute returns and greater technology risk than conventional fossil fuel generation.
Distribution-Level Interconnection Standards and State Implementation
The Energy Policy Act of 2005 established IEEE 1547 as the national standard for interconnection of distributed energy resources in the United States. IEEE 1547 establishes criteria and requirements for interconnection of distributed energy resources with electric power systems and associated interfaces. Currently, three quarters of the states have adopted, referenced, or incorporated IEEE 1547 in their state public utility commission interconnection rules.
State adoption of IEEE 1547 has accelerated, particularly following publication of the IEEE 1547-2018 revision. States including California, Hawaii, New York, and independent system operators including the California Independent System Operator and Pennsylvania, Jersey, Maryland Interconnection have mandated or transitioned to IEEE 1547-2018 as the baseline standard. However, substantial variation remains in state-level implementation, with individual states exercising significant flexibility in how they adapt IEEE 1547 requirements to their regulatory frameworks.
Distribution-level interconnection processes generally involve fewer studies and shorter timelines than transmission-level interconnection. However, utility-specific interconnection procedures, local permitting requirements, and the proliferation of distributed solar and storage resources have created new bottlenecks at the distribution level. The Department of Energy has announced funding to support adoption of interconnection software solutions and technical assistance for distribution utility modernization.
Grid Reliability and System Integration Challenges
The North American Electric Reliability Corporation maintains reliability standards for the bulk power system and increasingly focuses on integration of inverter-based resources, which now represent a substantial and rapidly growing portion of system capacity. NERC reliability standards have evolved to address the technical characteristics of solar, wind, and battery storage resources, which differ fundamentally from conventional synchronous generation.
Inverter-based resources create new technical challenges for grid stability. Unlike synchronous generators, which provide inherent inertia and fault current, inverter-based resources must be programmed to provide these services. NERC standards increasingly mandate requirements for grid-forming inverter capabilities, frequency response performance, and voltage support. These technical requirements can increase equipment costs and create additional interconnection study complexity.
The grid integration challenge extends to the quantity of resources now seeking interconnection. The 2,300 gigawatts in the active queue represents nearly twice the currently installed capacity of the United States power fleet. Integrating this volume of distributed and utility-scale resources requires substantial advances in transmission and distribution system planning, monitoring, and control. The extended timelines for both interconnection and transmission planning create timing mismatches that amplify grid integration challenges.
Open Questions
1. How quickly will FERC Order 2023 reforms reduce interconnection queue timelines, and what is the expected magnitude of improvement? Order 2023 implementation is underway, but the first full cycle of cluster studies under the new rules is not yet complete. Actual impacts on queue timelines will not be fully visible until 2025 or 2026. The question matters because current developer decisions regarding capital deployment depend on expectations of interconnection timing under the new regime.
2. Will transmission planning and cost allocation reforms establish sufficient capital to upgrade transmission systems to accommodate the 2,300 gigawatts of queued capacity? Order 1920 requires long-range transmission planning but does not guarantee funding. The question of whether adequate transmission system investment will materialize remains unresolved. The answer materially affects whether renewable energy deployment will be limited by transmission constraints rather than interconnection queue delays.
3. What is the economically optimal portfolio of grid-enhancing technologies, and how should interconnection study procedures allocate the costs of such technologies between incumbent ratepayers and interconnection customers? Grid-enhancing technologies can reduce network upgrade costs, but their capital costs and performance characteristics are not uniformly well understood across all transmission operators. Allocation of costs among beneficiaries remains contested.
4. How will state-level distribution utility interconnection procedures evolve as distributed solar and energy storage deployment accelerates? Distribution utilities are experiencing unprecedented interconnection request volumes, and utility-specific interconnection procedures create barriers to standardization. The question of whether regulatory intervention will require utility modernization at scale remains open.
5. Can the interconnection process be meaningfully streamlined without compromising grid reliability and affecting power quality for existing customers? Extended interconnection studies serve legitimate purposes in identifying network upgrades necessary for reliable operation. The question of whether study processes can be accelerated without reducing analytical rigor remains unresolved.
6. What will be the impact of climate change and increasing extreme weather events on interconnection study assumptions regarding future demand patterns, resource availability, and transmission system adequacy? Current interconnection studies and transmission planning processes incorporate historical climate data and demand patterns. Future climate scenarios may render current assumptions unreliable.
Source List
7. 1. Lawrence Berkeley National Laboratory, Energy Markets and Planning Program. Queued Up: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2024. 2025. Principal reference for interconnection queue statistics, project characteristics, and long-term outcome analysis.
8. 2. Federal Energy Regulatory Commission. Order No. 2023: Improvements to Generator Interconnection Procedures and Agreements. July 28, 2023. Foundational regulatory document establishing cluster study approach, co-location provisions, and affected system study reforms.
9. 3. Federal Energy Regulatory Commission. Order No. 1920: Building for the Future Through Electric Regional Transmission Planning and Cost Allocation. May 13, 2024. Primary source for transmission planning and cost allocation reforms.
10. 4. Federal Energy Regulatory Commission. Order No. 2023-A: Improvements to Generator Interconnection Procedures and Agreements, Requests for Rehearing and Clarification. March 21, 2024. Clarification order addressing rehearing requests regarding Order 2023 implementation.
11. 5. Council on Foreign Relations. The U.S. Interconnection Challenge: Why Renewables Are Stuck in Line. Comprehensive policy analysis of interconnection queue barriers and reform approaches.
12. 6. U.S. Department of Energy. Tackling High Costs and Long Delays for Clean Energy Interconnection. Federal initiative addressing interconnection bottlenecks and supporting state-level reforms.
13. 7. IEEE Standards Association. IEEE 1547-2018: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces. Technical standard establishing criteria for distribution-level resource interconnection.
14. 8. Concentric Energy Advisors. Clogged Interconnection Queues are Hindering Renewables Development, but Reforms are Underway. Market analysis of interconnection queue dynamics and reform impacts.
15. 9. Utility Dive. How Renewable Energy Producers Can Navigate FERCs New Interconnection Rules. 2024. Practitioner guidance on Order 2023 implementation.
16. 10. ScienceDirect. Grid Connection Barriers to Renewable Energy Deployment in the United States. 2024. Peer-reviewed analysis of technical, regulatory, and economic interconnection barriers.
17. 11. North American Electric Reliability Corporation. Reliability Guidelines: Interconnection Requirements for Inverter-Based Resources. Technical standards for grid-forming inverter requirements and performance.
18. 12. Zero Emission Grid. Interconnection Queues: The Obstacle in Renewable Projects. Analysis of interconnection queue economics and project viability impacts.
Bibliography
• Federal Energy Regulatory Commission. Order No. 1920: Building for the Future Through Electric Regional Transmission Planning and Cost Allocation. May 13, 2024. 18 C.F.R. Parts 35 and 157.
• Federal Energy Regulatory Commission. Order No. 2023: Improvements to Generator Interconnection Procedures and Agreements. July 28, 2023. 18 C.F.R. Parts 35 and 37.
• Federal Energy Regulatory Commission. Order No. 2023-A: Improvements to Generator Interconnection Procedures and Agreements, Requests for Rehearing and Clarification. March 21, 2024.
• IEEE Standards Association. IEEE 1547-2018: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces. 2018.
• Lawrence Berkeley National Laboratory, Energy Markets and Planning Program. Queued Up: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2024. 2025.
• Lawrence Berkeley National Laboratory, Energy Markets and Planning Program. U.S. Interconnection Queue Data Through 2024: Complete Interconnection Request Dataset and Summarized Data Workbook. 2025.
• North American Electric Reliability Corporation. Reliability Guidelines: Interconnection Requirements for Inverter-Based Resources. 2023.
• U.S. Department of Energy Office of Energy Efficiency and Renewable Energy. Tackling High Costs and Long Delays for Clean Energy Interconnection. 2024.
• U.S. Energy Information Administration. Annual Energy Outlook. 2025.
Interested in analysis about the intersection of tech, policy and the law? Check out my Substack channel. https://theinnovationattorney.substack.com/