Rare Earth Price Floor and Pentagon Offtake
Executive Summary
A price floor and Pentagon offtake make domestic rare earth processing financeable for a venture funded startup only when federal senior debt and secured feedstock accompany them. The floor removes commodity price risk and the offtake removes demand risk, the exposures a lender weighs first after the 2015 Molycorp bankruptcy. Neither pays for a separation plant, and in the startup financings the Pentagon has announced since July 2025 the instrument that does is a federal loan.
The reference transaction is the July 10, 2025 agreement with MP Materials: $400 million of convertible preferred stock, a ten year floor of $110 per kilogram on NdPr oxide, and ten year purchase of all magnets from a new facility. The Pentagon’s stake is about 15 percent on conversion and exercise, and commentary describing it as 50 percent overstates it. Market prices sat within about 5 percent of the floor in July 2026.
Three later structures show how a startup could be financed. Phoenix Tailings received a $500 million conditional loan commitment on June 16, 2026. Vulcan Elements received a $620 million loan alongside $550 million of private capital in November 2025. On August 24, 2026 the Department of War committed $750 million to a $1.55 billion vehicle for Serra Verde, with take or pay offtake and floors of $575 per kilogram on dysprosium and $2,050 on terbium.
Established: the floor and loan instruments exist and have been used. Evolving: China’s suspension of its October 2025 export controls expires on November 10, 2026; the January 1, 2027 deadline on Chinese origin magnets faces lobbying for delay; new Pentagon lending authority expires on October 1, 2028; and every federal startup commitment is conditional on diligence.
Detailed Findings
What Did the Pentagon Agree to with MP Materials in July 2025?
The Pentagon agreed on July 10, 2025 to buy $400 million of convertible preferred stock in MP Materials, receive a warrant to purchase common shares at $30.03, guarantee a floor of $110 per kilogram on NdPr oxide for ten years, and buy all magnets produced at a new 10X facility for ten years after commissioning, which was targeted for 2028. On conversion and exercise the Pentagon would hold about 15 percent of the common shares and become the largest shareholder. Some commentary describes the stake as 50 percent. The announced figure is about 15 percent, and this report uses it.
The package also carried a $150 million Pentagon loan to support the Mountain Pass expansion and a $1 billion financing commitment from two large investment banks for the 10X facility. The floor works as a price protection agreement in which the Pentagon pays the difference between $110 and the realized price on NdPr products. For the quarter ended June 30, 2026, MP reported 1,006 metric tons of NdPr sales, $94.4 million of NdPr oxide and metal revenue and $17.6 million of price protection income. Price protection income was $59.9 million for the first half of 2026.
Dividing revenue by tons gives about $93.80 per kilogram. Dividing price protection income by tons adds about $17.50. The sum, about $111.30, shows the mechanism lifting realized revenue to the floor. The calculation is mine and mixes oxide equivalent and metal volumes, so it is approximate. For a startup, the floor converts commodity price risk into credit risk on the Pentagon, a counterparty lenders already underwrite.
MP carries advantages a startup lacks. At June 30, 2026 it held $1,452.6 million of cash and short term investments, $934.6 million of long term debt, $1,608.6 million of net property, plant and equipment, and an operating mine. Its capital additions were $307.7 million in the first half of 2026 alone. A floor attached to a company with that balance sheet is a different credit than a floor attached to a Series B company with a pilot line.
How Is the $110 per Kilogram Floor Performing Against Market Prices in 2026?
The floor sits close to the market, so it currently insures against a price collapse and subsidizes little. A price reporting agency assessed NdPr oxide delivered to North America at $120 per kilogram in June 2026 and $115 in July, and assessed the China free on board price at $112 in July. In August 2026 traders reported some sales below $110, and developers told reporters the $110 level is high enough to bring planned projects into production.
The floor was roughly double the market price when announced in July 2025, which is the context in which it was designed. The history behind the design is dysprosium oxide, which peaked above $2,300 per kilogram in 2011 and fell below $200 by 2016. Molycorp filed for bankruptcy in 2015 with $1.7 billion of debt and was later sold for $20.5 million. A lender who remembers that sequence underwrites the downside price first, and a contractual floor answers that concern.
Japan and Australia built a parallel instrument. A Japanese state backed investor and Lynas revised a deal in March 2026 that sets a $110 per kilogram floor on 5,000 metric tons of NdPr, with the investor receiving 30 percent of the upside above $150 per kilogram, capped at $10 million per year. Two allied governments have now priced NdPr at the same $110 level, which gives lenders a reference point that does not depend on a single contract.
Which Startups Have Received Federal Backing Since 2025 and on What Terms?
Federal backing for startups has taken the form of loans and equity linked warrants, and the announcements reviewed for this report disclose no price floor for any startup. Phoenix Tailings closed a $43 million Series B led by Envisioning Partners with participation from In-Q-Tel, Yamaha Motor Ventures, BMW i Ventures and other investors. On June 16, 2026 the Pentagon’s Office of Strategic Capital (OSC) announced a $500 million conditional loan commitment to the company, part of an initiative of roughly $1 billion in total financing. No funds disburse until the company clears financial, legal and technical diligence.
The planned Freedom Facility combines separation and metallization for NdPr, dysprosium and terbium, with initial operations targeted for 2028. Feedstock would come from tailings ponds, recycled magnets and industrial byproducts. At announcement Phoenix had disclosed neither a site nor public feedstock supply agreements, and its separation technology was in a Department of Energy backed demonstration phase with MIT and the University of Minnesota. BMW and Yamaha are named supply partners, with agreements reported to exceed $100 million in total value. The Exeter, New Hampshire facility, opened in October 2025, targets more than 1,000 tonnes of annual capacity.
Vulcan Elements, a privately held North Carolina magnet maker, announced on November 3, 2025 a $620 million OSC loan, $50 million from the Department of Commerce under the CHIPS and Science Act, and $550 million of private capital to build a 10,000 metric ton magnet facility. The Department of War receives warrants in Vulcan and in ReElement Technologies, the refiner, which received an $80 million OSC loan matched by private capital. The Department of Commerce takes $50 million of equity in Vulcan.
In June 2026 Energy Fuels, a public company, received a conditional commitment of up to $725 million of senior secured debt with a 20 year tenor from OSC, subject to diligence, final agreements and approvals. Across these four financings the federal government supplies senior debt, takes warrants or equity, and leaves the price floor for a separate instrument.
What Does the Serra Verde Structure Add for Heavy Rare Earths?
The Serra Verde vehicle adds a complete commercial package for heavy rare earths: price floors, an escalator, an upside share, take or pay offtake and working capital. Announced on August 24, 2026, the $1.55 billion special purpose vehicle is backed by $750 million from the Department of War, raised from $500 million, plus a $500 million senior secured revolving credit facility from a large bank for working capital. The floors are $575 per kilogram for dysprosium, $2,050 per kilogram for terbium and $110 per kilogram for NdPr, each escalating 2 percent annually. Serra Verde keeps 70 percent of any price above the floor.
The vehicle must accept contracted output or pay a penalty for volume it does not take, which makes the offtake take or pay. The Defense Logistics Agency made a forward purchase commitment of at least $300 million over five years. One account reports the offtake term as six years for all phase one output of four magnet elements. USA Rare Earth is acquiring Serra Verde at an implied equity value of about $2.8 billion, consisting of $300 million of cash and about 126.85 million new shares, and Brazil’s antitrust authority is reviewing the merger.
The Pela Ema mine produces about 4,000 metric tons of total rare earth oxide equivalent a year and targets about 6,400 by the end of 2027. Its mixed carbonate goes to China for separation under an arrangement that expires at the end of 2026. Carester’s Caremag plant in Lacq, France is due to commission in late 2026 with planned annual output of 800 tonnes of NdPr oxide, 500 tonnes of dysprosium oxide and 100 tonnes of terbium oxide. The structure shows what a startup processor should ask a federal buyer to sign, and it shows that the separation step is the bottleneck a processor can own.
What Do Lenders Require Before They Fund a Rare Earth Separation Plant?
Lenders require a feedstock agreement, an offtake agreement with a counterparty they can underwrite, and an independent engineer’s confirmation that the technology works at plant size. In hardware financings I have worked on, those three documents come before any term sheet, and a price floor sits inside only one of them. A floor tells the lender what the revenue line is worth. It says nothing about whether concentrate will arrive at the gate or whether the circuit will hold its recovery at commercial throughput.
As a chemist, I read a separation circuit as a count of stages. Neighboring lanthanides differ so little in chemistry that solvent extraction chains a very large number of mixer settler stages to reach oxide purity, and each stage adds inventory, reagent consumption and opportunity for the circuit to drift. A pilot that performs on a clean feed can behave differently on tailings or recycled magnet feed. This is first of a kind completion risk, and lenders price it separately from price risk.
A heavy rare earth benchmark from the public market shows the order of magnitude. Energy Fuels targets about $104 million of capital cost for a heavy rare earth oxide expansion at its White Mesa Mill in Utah, with capacity of up to about 120 tonnes of dysprosium oxide and 20 tonnes of terbium oxide per year, plus samarium, europium and gadolinium. It targets commissioning of the terbium and dysprosium circuits by the fourth quarter of 2027, funded by a conditional federal loan and about $0.96 billion of working capital as of March 31, 2026. A company with a licensed, operating mill and that cash position carries this project. A startup building a first plant on a greenfield site carries a larger completion risk.
Where Does Venture Capital Fit in the Capital Stack?
Venture capital fits at the technology proof and pilot stage, as first loss equity ahead of a financial investment decision. A $43 million Series B is the right size to fund pilot operations, engineering and a feedstock option. It cannot fund a plant that OSC sized at $500 million for Phoenix or $620 million for Vulcan. In the Vulcan structure the private capital of $550 million sits alongside the federal loan, which means a venture backed company must attract project equity from infrastructure investors or strategic buyers at the plant stage.
A conditional federal commitment changes how a venture term sheet should be written. The Phoenix commitment disburses only after diligence, so an investor can tie each tranche of its own funding to the loan’s closing. Warrants granted to the Department of War dilute existing holders and need to be reflected in protective provisions and pro rata rights. A founder who accepts a conditional commitment as if it were a funded loan invites a down round if diligence fails, because the cap table will already assume a plant that does not yet have its debt.
What Policy Developments Since January 2026 Affect Price Certainty?
Policy since January 2026 has moved toward a broader floor, and none of it has produced a binding price mechanism for startups. In January 2026 the administration indicated interest in minimum import prices for certain critical minerals. In early February 2026 the United States and Mexico signed an action plan with a 60 day window to study price floors. On February 4, 2026 the United States, the European Commission and Japan issued a joint statement that listed four options: border adjusted price floors, standards based markets, price gap subsidies and offtake agreements.
The February 2026 critical minerals ministerial drew more than 50 delegations and launched the Forum on Resource Geostrategic Engagement. The Export-Import Bank approved up to $10 billion in loans for Project Vault, a strategic minerals reserve that also draws on about $2 billion of private capital. A lending authority of $100 billion has also been cited in discussions of how a floor might be financed.
In March 2026 the Office of the United States Trade Representative requested comments on a plurilateral agreement on trade in critical minerals, with the comment period ending March 19, and a United States and Japan action plan is dated the same day. In June 2026 the House passed the DOMINANCE Act, H.R. 7037, which codifies United States participation in the forum, and in July 2026 the forum formed working groups on project investment and policy coordination. A border adjusted floor would lift the price that every producer receives and every buyer pays. A contract floor pays the one producer that signed it, and a startup today can obtain only the contract floor.
Cost constrains any broad floor. A 2024 estimate put the cost of price support for lithium alone at $7.5 billion over five years, and that figure assumed a Department of Energy program and a different price level than any floor now under discussion. No public cost estimate for a rare earth floor appeared in the record reviewed for this report, and a call for transparent cost modeling under multiple price scenarios remains unmet.
How Does China’s Export Control Calendar Affect Offtake Risk?
China’s calendar determines whether a floor pays out or whether the market lifts above it. China’s April 2025 controls, which require case by case licenses for samarium, gadolinium, terbium, dysprosium, lutetium, scandium and yttrium, remain in force. China’s October 2025 expansion, including extraterritorial licensing for foreign products containing Chinese origin rare earths down to a 0.1 percent value threshold, was suspended on November 7, 2025 until November 10, 2026. As of October 6, 2026 Beijing had not said whether it would extend, narrow or let the suspension lapse.
On June 22, 2026 China added 10 American companies, including MP Materials and USA Rare Earth, to its export control list, barring Chinese dual use exports to them, four days after the Energy Fuels loan announcement. Exports of yttrium, dysprosium and terbium to the United States are reported to run about 50 percent below their pre restriction baseline. China holds about 60 percent of global rare earth mining and more than 85 percent of processing by widely cited estimates.
The defense procurement deadline adds demand pull. Clause 252.225-7052 of the Defense Federal Acquisition Regulation Supplement bars samarium cobalt and NdFeB magnets from defense contracts if any production stage from mining through fabrication occurred in China, Russia, Iran or North Korea, starting January 1, 2027. Major defense contractors have lobbied for a second delay, arguing that no Western alternative has reached the required volumes. A floor behaves like a put option for the producer: if China relaxes and prices fall, the floor pays; if China tightens and prices rise, the upside share or spot sales pay. The deadline determines whether the offtake buyers have a compliance reason to sign.
What Legal Limits Constrain Federal Price Floors and Loans?
Federal price floors and loans are bounded by appropriations, statutory authority and contract termination rights. The Anti-Deficiency Act, 31 U.S.C. 1341, bars an agency from obligating funds beyond an appropriation, so a ten year floor is either a contingent commitment subject to appropriations or sits in a vehicle that already holds the money, which is how the Serra Verde vehicle is built. Section 303 of the Defense Production Act, codified at 50 U.S.C. 4533, authorizes purchase commitments and subsidy payments for domestically produced materials, requires written presidential determinations, and requires notice to Congress for actions above $50 million in aggregate unless waived in an emergency.
OSC is established by 10 U.S.C. 149 and may make loans and loan guarantees subject to appropriations, but its authority to make new loans and loan guarantees expires on October 1, 2028. A startup that reaches financial close after that date depends on reauthorization. Federal supply contracts also carry termination for convenience rights under the Federal Acquisition Regulation, so a lender must read the offtake for how the government pays out on termination and whether the floor survives it.
The tax credit under Section 45X provides 10 percent of qualifying production costs for critical minerals. Under Public Law 119-21 the credit is 100 percent of that rate for production through 2030, 75 percent in 2031, 50 percent in 2032 and 25 percent in 2033, and it expires after 2033. A plant commissioned in 2028 captures three full years and then watches the credit decline, which affects the debt sizing in the later years of a twenty year loan.
What Does the Arithmetic Look Like for a Startup Processor?
The arithmetic shows that a floor makes the revenue line bankable and that the plant cost still needs debt. Take a hypothetical 1,000 metric ton per year NdPr oxide producer. At the $110 floor its revenue is $110 million a year. At the Serra Verde heavy rare earth floors, a producer with the Energy Fuels stated capacity of 120 tonnes of dysprosium oxide and 20 tonnes of terbium oxide would earn $69 million from dysprosium and $41 million from terbium, a total of $110 million, against a stated capital cost of $104 million. These are gross revenues before feedstock and operating costs, and the capacities and floors come from different companies.
Now assume, for illustration only, that operating costs consume $60 million of the $110 million. The remaining $50 million supports annual debt service of about $38.5 million at a 1.3 times coverage ratio. At an assumed 8 percent interest rate over a 20 year amortization, that debt service supports about $378 million of senior debt. The assumptions are mine and are not drawn from any company. They show that a bankable floor lets a lender size meaningful debt, and that the outcome depends on operating cost, which only feedstock and technology performance determine.
What Should a Venture Funded Founder Do Before Asking Lenders for a Term Sheet?
A founder should secure feedstock first, then negotiate an offtake with a floor, then time financial close against the federal calendar. A feedstock agreement answers the question lenders ask first and the one Phoenix had not answered publicly at announcement. An offtake with the Defense Logistics Agency or a defense prime should carry take or pay terms, a floor with an escalator, a floor tenor that matches the debt, and clear payment terms on termination. The Serra Verde terms give a negotiating reference.
Financial close needs to land before October 1, 2028 if OSC is the lender, and the plant needs to be producing qualified material in time for buyers facing the January 1, 2027 magnet rule or its delayed successor. A heavy rare earth and metallization capability carries more of the economics than a light rare earth line, because dysprosium and terbium are the elements China licenses and because the floors of $575 and $2,050 per kilogram sit well above the dysprosium price of under $200 in 2016. Equity investors should tranche their funding to the federal loan’s closing and carry cap table room for government warrants.
The next piece in this series takes up the offtake contract itself: how a take or pay purchase commitment from a federal buyer reads from the lender’s side, clause by clause, including termination for convenience, payment on termination and what survives when appropriations lapse.
Want more industry insights? I publish daily analysis on the intersection of deep tech and venture law.
Open Questions
Whether China extends, narrows or lets lapse the suspension that expires on November 10, 2026 will move prices more than any contract. A lapse restores the October 2025 controls, including extraterritorial licensing, and lifts ex China prices. An extension keeps the floor close to the market. Investors in a first plant need to model both cases because the plant will operate through whichever one occurs.
Whether the Pentagon holds the January 1, 2027 magnet deadline in Clause 252.225-7052 determines whether defense primes have a compliance reason to sign multi year offtakes. Contractors have lobbied for a delay. A delay shortens the demand pull a startup can show a lender.
Whether Congress extends OSC’s new lending authority past October 1, 2028 determines whether a startup that misses a 2028 financial close has a federal lender at all. Phoenix targets initial operations in 2028 and has not disclosed a site, so its schedule is already close to the line.
Whether conditional commitments convert to funded loans for first of a kind plants has no completed example in the record reviewed. Phoenix, Energy Fuels and Vulcan each hold announced commitments subject to diligence, and the public record shows no disbursement figures. Investors need to know the conversion rate and the diligence conditions that matter, which the Pentagon has not detailed publicly.
Whether the administration builds a border adjusted floor or a plurilateral reference price system, and who pays for it, remains undecided. A contract floor helps the company that signed it. A reference price reaches every producer and raises costs for every buyer. Cost modeling for rare earths under multiple scenarios has not been published, and the lithium estimate of $7.5 billion over five years shows the size of the exposure.
Source List
Primary source. 10 U.S.C. 149, Office of Strategic Capital. Cornell Legal Information Institute. https://www.law.cornell.edu/uscode/text/10/149. Establishes the Pentagon lending office, its loan and loan guarantee authority, and the October 1, 2028 expiration of new lending authority.
Primary source. 50 U.S.C. 4533, Defense Production Act section 303. Cornell Legal Information Institute. https://www.law.cornell.edu/uscode/text/50/4533. Authorizes purchase commitments and subsidy payments for domestic materials and sets the congressional notice threshold of $50 million.
Primary source. MP Materials, Reports Second Quarter 2026 Results, August 6, 2026. https://mpmaterials.com/news/mp-materials-reports-second-quarter-2026-results. First party figures for NdPr sales, revenue, price protection income, capital additions and liquidity.
Secondary source. Congressional Research Service, The Section 45X Advanced Manufacturing Production Credit, In Focus IF12809, August 13, 2026. https://www.everycrsreport.com/files/2026-08-13_IF12809_6951a5de81763ce42e359ec101d527e70bf9ff16.html. Describes the critical minerals credit rate and its phase out under Public Law 119-21.
Secondary source. Spiller, Beia, and Madeline Craig Scheckman. Can Price Floors Fix America’s Rare Earth Problem? Resources for the Future, April 22, 2026. https://www.resources.org/common-resources/can-price-floors-fix-americas-rare-earth-problem/. Analyzes the cost and design of federal price guarantees for rare earths.
Secondary source. Shokravi, Hashem, Daniel Weiss, and Beia Spiller. Renewed Efforts at Multilateralism in the Critical Minerals Sector. Resources for the Future Issue Brief 26 05, August 25, 2026. https://www.rff.org/publications/issue-briefs/renewed-efforts-at-multilateralism-in-the-critical-minerals-sector/. Source for Project Vault financing, FORGE, the DOMINANCE Act and the Lynas floor terms.
Industry publication. S&P Global Energy. Rare Earths: NdPr Oxide Sales Heard Below Support Levels of $110 per Kilogram CIF North America. August 18, 2026. https://www.spglobal.com/energy/en/news-research/latest-news/metals/081826-rare-earths-ndpr-oxide-sales-heard-below-support-levels-of-110kg-cif-north-america. Gives July and August 2026 NdPr price assessments.
Industry publication. Tech Times. Pentagon Locks First Price Floors on Dysprosium, Terbium in $1.55B Brazil Rare Earth Deal. August 26, 2026. https://www.techtimes.com/articles/325689/20260826/pentagon-locks-first-price-floors-dysprosium-terbium-155b-brazil-rare-earth-deal.htm. Source for the Serra Verde vehicle floors, escalator, take or pay terms and financing.
Industry publication. Roan, A.J. Pentagon Locks in $1.55B Rare Earth Deal. Metal Tech News, August 26, 2026. https://www.metaltechnews.com/story/2026/08/26/tech-metals/pentagon-locks-in-155b-rare-earth-deal/2926.html. Confirms the $750 million Department of War investment and the reported six year offtake term.
Industry publication. Adamas Intelligence. U.S. Defense Contractors Seek Second DFARS Delay. June 5, 2026. https://www.adamasintel.com/u-s-defense-contractors-seek-second-dfars-delay-as-pentagons-200b-deal-team-six-mobilizes-for-rare-earth-independence/. Describes the January 1, 2027 enforcement date and the contractor request for delay.
Industry publication. Crux Investor. Energy Fuels Begins Heavy Rare Earth Plant Construction in Utah Targeting $104 Million Expansion. 2026. https://www.cruxinvestor.com/posts/energy-fuels-begins-heavy-rare-earth-plant-construction-in-utah-targeting-104-million-expansion. Source for heavy rare earth capacity, capital cost and commissioning targets.
Industry publication. Pulse 2. Energy Fuels Receives Conditional $725 Million Financing Commitment From U.S. Government. June 21, 2026. https://pulse2.com/energy-fuels-receives-conditional-725-million-financing-commitment-from-u-s-government/amp/. Gives the terms of the federal commitment to Energy Fuels.
Industry publication. GovConFeed. Pentagon Commits $500M Conditional Loan to Phoenix Tailings to Build Domestic Rare Earth Freedom Facility. June 2026. https://govconfeed.com/article/pentagon-500m-loan-phoenix-tailings-rare-earth-freedom-facility-june-2026. Source for the Phoenix Tailings commitment, facility plans and undisclosed site and feedstock.
Industry publication. Argus Media. BMW, Yamaha Invest in RE Start Up Phoenix Tailings. https://www.argusmedia.com/metals-platform/newsandanalysis/article/2643658-BMW–Yamaha-invest-in-RE-start-up-Phoenix-Tailings. Gives the $43 million Series B and its investors.
Industry publication. Benchmark Mineral Intelligence. Bostock, Didi. US Critical Mineral Price Support Could Cost $7.5 Billion Alone for Lithium in Next Five Years. September 26, 2024. https://source.benchmarkminerals.com/article/us-critical-mineral-price-support-could-cost-7-5-billion-alone-for-lithium-in-next-five-years. Source for the lithium price support cost estimate.
News source. Mining.com. MP Materials Lands Multi Billion Pentagon Deal. July 10, 2025. https://www.mining.com/?p=1183185. Source for the July 2025 MP Materials preferred stock, warrant, floor, offtake and financing terms.
News source. Mining.com. Vulcan Elements, ReElement Technologies Sign $1.4B Rare Earth Magnet Supply Deal With US. November 3, 2025. https://www.mining.com/?p=1192089. Source for the Vulcan and ReElement loans, warrants and private capital.
News source. Bloomberg Government. China Formalizes Rare Earth Curbs Suspension After Trade Truce. November 7, 2025. https://news.bgov.com/international-trade/china-formalizes-rare-earth-curbs-suspension-after-trade-truce. Confirms the suspension through November 10, 2026.
News source. Startup Fortune. Schulze, Walter. China’s Rare Earth Export Truce Expires November 10 With No Renewal in Sight. October 6, 2026. https://startupfortune.com/chinas-rare-earth-export-truce-expires-november-10-with-no-renewal-in-sight/. Describes what remains suspended and what controls stay in force.
News source. Foreign Policy in Focus. Khalid, Imran. China Strikes Back at the Pentagon’s Rare Earth Bet. June 23, 2026. https://fpif.org/china-strikes-back-at-the-pentagons-rare-earth-bet/. Source for the June 22, 2026 Chinese export control listings and secondary market share figures that this report treats as reported and not verified.
News source. IMA. US Critical Minerals Talks Advance With EU, Japan on Price Floor. March 13, 2026. https://ima-api.org/us-critical-minerals-talks-advance-with-eu-japan-on-price-floor/. Source for the February 4, 2026 joint statement options and the Mexico action plan.
Bibliography
Adamas Intelligence. U.S. Defense Contractors Seek Second DFARS Delay as Pentagon’s $200B Deal Team Six Mobilizes for Rare Earth Independence. June 5, 2026. https://www.adamasintel.com/u-s-defense-contractors-seek-second-dfars-delay-as-pentagons-200b-deal-team-six-mobilizes-for-rare-earth-independence/.
Argus Media. BMW, Yamaha Invest in RE Start Up Phoenix Tailings. Undated. https://www.argusmedia.com/metals-platform/newsandanalysis/article/2643658-BMW–Yamaha-invest-in-RE-start-up-Phoenix-Tailings.
Bloomberg Government. China Formalizes Rare Earth Curbs Suspension After Trade Truce. November 7, 2025. https://news.bgov.com/international-trade/china-formalizes-rare-earth-curbs-suspension-after-trade-truce.
Bostock, Didi. US Critical Mineral Price Support Could Cost $7.5 Billion Alone for Lithium in Next Five Years. Benchmark Mineral Intelligence, September 26, 2024. https://source.benchmarkminerals.com/article/us-critical-mineral-price-support-could-cost-7-5-billion-alone-for-lithium-in-next-five-years.
Congressional Research Service. The Section 45X Advanced Manufacturing Production Credit. In Focus IF12809. August 13, 2026. https://www.everycrsreport.com/files/2026-08-13_IF12809_6951a5de81763ce42e359ec101d527e70bf9ff16.html.
Crux Investor. Energy Fuels Begins Heavy Rare Earth Plant Construction in Utah Targeting $104 Million Expansion. 2026. https://www.cruxinvestor.com/posts/energy-fuels-begins-heavy-rare-earth-plant-construction-in-utah-targeting-104-million-expansion.
Foreign Policy in Focus. Khalid, Imran. China Strikes Back at the Pentagon’s Rare Earth Bet. June 23, 2026. https://fpif.org/china-strikes-back-at-the-pentagons-rare-earth-bet/.
GovConFeed. Pentagon Commits $500M Conditional Loan to Phoenix Tailings to Build Domestic Rare Earth Freedom Facility. June 2026. https://govconfeed.com/article/pentagon-500m-loan-phoenix-tailings-rare-earth-freedom-facility-june-2026.
IMA. US Critical Minerals Talks Advance With EU, Japan on Price Floor. March 13, 2026. https://ima-api.org/us-critical-minerals-talks-advance-with-eu-japan-on-price-floor/.
Mining.com. MP Materials Lands Multi Billion Pentagon Deal. July 10, 2025. https://www.mining.com/?p=1183185.
Mining.com. Vulcan Elements, ReElement Technologies Sign $1.4B Rare Earth Magnet Supply Deal With US. November 3, 2025. https://www.mining.com/?p=1192089.
MP Materials. MP Materials Reports Second Quarter 2026 Results. August 6, 2026. https://mpmaterials.com/news/mp-materials-reports-second-quarter-2026-results.
Pulse 2. Energy Fuels Receives Conditional $725 Million Financing Commitment From U.S. Government. June 21, 2026. https://pulse2.com/energy-fuels-receives-conditional-725-million-financing-commitment-from-u-s-government/amp/.
Roan, A.J. Pentagon Locks in $1.55B Rare Earth Deal. Metal Tech News, August 26, 2026. https://www.metaltechnews.com/story/2026/08/26/tech-metals/pentagon-locks-in-155b-rare-earth-deal/2926.html.
S&P Global Energy. Rare Earths: NdPr Oxide Sales Heard Below Support Levels of $110 per Kilogram CIF North America. August 18, 2026. https://www.spglobal.com/energy/en/news-research/latest-news/metals/081826-rare-earths-ndpr-oxide-sales-heard-below-support-levels-of-110kg-cif-north-america.
Schulze, Walter. China’s Rare Earth Export Truce Expires November 10 With No Renewal in Sight. Startup Fortune, October 6, 2026. https://startupfortune.com/chinas-rare-earth-export-truce-expires-november-10-with-no-renewal-in-sight/.
Shokravi, Hashem, Daniel Weiss, and Beia Spiller. Renewed Efforts at Multilateralism in the Critical Minerals Sector. Resources for the Future Issue Brief 26 05. August 25, 2026. https://www.rff.org/publications/issue-briefs/renewed-efforts-at-multilateralism-in-the-critical-minerals-sector/.
Spiller, Beia, and Madeline Craig Scheckman. Can Price Floors Fix America’s Rare Earth Problem? Resources for the Future, April 22, 2026. https://www.resources.org/common-resources/can-price-floors-fix-americas-rare-earth-problem/.
Tech Times. Pentagon Locks First Price Floors on Dysprosium, Terbium in $1.55B Brazil Rare Earth Deal. August 26, 2026. https://www.techtimes.com/articles/325689/20260826/pentagon-locks-first-price-floors-dysprosium-terbium-155b-brazil-rare-earth-deal.htm.
U.S. Code. Title 10, section 149, Office of Strategic Capital. https://www.law.cornell.edu/uscode/text/10/149.
U.S. Code. Title 50, section 4533, Other Presidential Action Authorized. https://www.law.cornell.edu/uscode/text/50/4533.
Interested in analysis about the intersection of tech, policy and the law? Check out my Substack channel. https://theinnovationattorney.substack.com/