Status, Fuel, Authorization, and Deadlines
Executive Summary
Project Pele is a 1.5 megawatt transportable gas cooled microreactor that BWXT is building for the Strategic Capabilities Office, with testing at Idaho National Laboratory targeted for 2027.
The reactor is a high temperature gas cooled design fueled with TRISO particles made from high assay low enriched uranium, and it will supply power to an Idaho test grid for about three years. Testing and operation fall under Department of Energy authorization, which places the prototype outside the licensing jurisdiction of the Nuclear Regulatory Commission. The program began in 2016, the prime contract of about $300 million went to BWXT in June 2022, and the original target of a reactor running in Idaho before the end of 2025 has moved to 2027 for formal testing and 2028 for electricity.
Remote site operators, utilities, data center developers, and investors in advanced reactor suppliers follow Pele because it is the first test of whether a shipping container sized reactor can be built in a factory, moved by truck, rail, or aircraft, fueled, and operated on a published schedule. Core stacking at the BWXT campus in Lynchburg, Virginia finished in June 2026, BWXT crews installed the core barrel in late summer 2026, and a full core of 40,000 TRISO fuel compacts has been in Idaho since November 5, 2025.
Section 110(b) of the Atomic Energy Act, 42 U.S.C. § 2140(b), lifts the licensing requirement for military utilization facilities, and Executive Order 14299 of May 2025 sets September 30, 2028 for an Army regulated reactor on a domestic military installation. Pele results therefore feed the schedule of the follow on Janus program.
Detailed Findings
What Is Project Pele and Who Is Building It?
Project Pele is a prototype transportable microreactor program run by the Strategic Capabilities Office, and BWXT Advanced Technologies of Lynchburg, Virginia serves as prime contractor and builder.
The program began in 2016 after a Defense Science Board study. The Strategic Capabilities Office issued a Notice of Intent for environmental review in March 2020 and opened a two year design competition among BWXT, Westinghouse, and X energy. BWXT won the prototype contract in June 2022 in an award reported at about $300 million, with two years allotted to deliver a prototype to Idaho. In September 2023 the office exercised a one year option with X energy to advance a second design, the Xe Mobile.
Rolls Royce LibertyWorks and Northrop Grumman contribute control and power conversion systems, and Torch Technologies handles module logistics. BWXT carries integration of the whole plant.
How Does the Pele Reactor Work?
Pele is a high temperature gas cooled reactor that turns heat from graphite embedded TRISO fuel into 1.5 megawatts of electricity, inside the 1 megawatt to 5 megawatt range the program originally specified.
Each TRISO particle is a uranium kernel roughly a millimeter across, wrapped in a porous carbon buffer, an inner pyrolytic carbon layer, a silicon carbide layer, and an outer pyrolytic carbon layer. The silicon carbide layer acts as a miniature pressure vessel and retains fission products at temperatures far above normal operation. In the compact form used by Pele, thousands of particles sit in a graphite matrix, the graphite slows neutrons and conducts heat, and a circulating gas carries the heat out of the core. Public materials describe the coolant only as a gas.
The plant ships as four standard 20 foot ISO containers, each about 8 feet wide and 8 feet high, holding the reactor module, an intermediate heat exchange module, a control module, and a power conversion module. A concrete shield structure at Idaho houses three of the four containers. BWXT states that the design meets shock and vibration requirements for transport by truck, train, and aircraft, and that digital twins captured during manufacturing support repeatable future builds.
Aboard a nuclear submarine I stood watches on a reactor plant qualified to survive shock, tilt, and tired operators. The transport requirement is the hardest engineering demand in Pele, because a reactor that must be lifted, trucked, and reassembled near a mission site inherits every one of those conditions without a shipyard behind it. BWXT’s claim that the plant offsets up to 1.5 million gallons of diesel and hundreds of fuel truck deliveries each year describes the commercial promise that the transport requirement must support.
What Fuel Does Project Pele Use and Where Is It Now?
Pele uses TRISO fuel made from high assay low enriched uranium, and a full core of 40,000 compacts arrived at Idaho National Laboratory on November 5, 2025.
High assay low enriched uranium is uranium enriched above 5 percent and below 20 percent in uranium 235, and public sources do not state the exact enrichment for Pele. BWXT manufactured the compacts at its Specialty Fuels Fabrication Group in Lynchburg and shipped them to the Transient Reactor Test Facility at Idaho. A 2022 program announcement reported that the fuel would be produced from material in the highly enriched uranium inventory of the Department of Energy. Qualification data for TRISO fuel came from the Advanced Gas Reactor TRISO Fuel Qualification Program run by the Office of Nuclear Energy at Idaho and Oak Ridge National Laboratory.
Where Does the Schedule Stand and Why Did It Slip?
The Pele reactor is expected to ship to Idaho in 2027, fuel and test there, and run for three years, which places electricity production in 2028, about three years after the target stated in 2023.
In August 2023 the program manager stated a goal of a reactor operating at Idaho before the end of 2025. The June 2022 award allotted two years for delivery of a prototype. The milestone record since then runs as follows: Department of Energy authorization of long lead item orders in December 2022, completion of the system design review in August 2024, the start of site construction at the Critical Infrastructure Test Range Complex at Idaho on September 24, 2024, start of core fabrication in July 2025, completion of fuel production in November 2025, completion of core stacking in June 2026, and installation of the core barrel in late summer 2026. An earlier plan called for transport to Idaho in 2026. No public document assigns the slip to a single cause, and the sequence of milestones shows a schedule built around first of a kind fabrication of the core and the fuel.
What Does Project Pele Cost and What Does the Money Buy?
The prime contract is reported at about $300 million, which divided by the energy the prototype can produce over three years gives roughly $7,600 per megawatt hour.
At 1.5 megawatts of continuous output, the reactor generates 13,140 megawatt hours per year and 39,420 megawatt hours over three years. Dividing $300 million by 39,420 yields about $7,610 per megawatt hour. That figure blends development, tooling, fuel qualification, and demonstration costs with generation, and it describes a prototype contract. A production unit would carry a different price. BWXT cites digital twins and precision tooling as the basis for repeatable future builds, and production economics depend on a proposed TRISO fuel plant, a point developed in the Open Questions section.
How Does Project Pele Connect to the Army Janus Program?
Janus is the Army program for an operating microreactor on a military installation, and BWXT’s Pele work informs its design.
BWXT is expected to build and operate a high temperature gas cooled reactor it calls BANR at Fort Campbell, Kentucky, under Janus. In November 2025 nine sites were selected for possible Janus deployment, and program documentation reported an operating goal of 2030. Executive Order 14299 is stricter: Section 3(a) directs the Secretary of Defense, through the Secretary of the Army, to commence operation of a nuclear reactor regulated by the United States Army at a domestic military base or installation no later than September 30, 2028. BWXT lists that date as its target. A separate Air Force program, the Advanced Nuclear Power for Installations effort launched in 2024, aims for two operating microreactors by 2030, and on April 13, 2026 the Air Force and the Defense Innovation Unit selected Buckley Space Force Base in Colorado and Malmstrom Air Force Base in Montana as potential sites.
Legal and Regulatory Implications
Who Regulates Project Pele if the Nuclear Regulatory Commission Does Not?
The Department of Energy authorizes and oversees Project Pele at Idaho, and the Nuclear Regulatory Commission holds no licensing authority over the prototype.
The Pentagon and the Department of Energy agreed that Pele will be tested and operated under Department of Energy authorization at a Department of Energy site. Testing begins only after the final safety review is complete. Department of Energy nuclear facilities must maintain a documented safety analysis under 10 C.F.R. Part 830, Subpart B. For military reactors, Section 110(b) of the Atomic Energy Act, 42 U.S.C. § 2140(b), provides that the license requirement does not apply to the manufacture, production, or acquisition of a utilization facility authorized under 42 U.S.C. § 2121, or to its use by the military or a contractor. The public record I reviewed does not cite the specific provision supporting the Department of Energy path for Pele.
The Nuclear Regulatory Commission contributed through public meetings of its Advisory Committee on Reactor Safeguards in late 2023, as part of a transportation analysis for future public road transport led by Pacific Northwest National Laboratory. A fueled mobile reactor moving on public roads engages the Department of Transportation hazardous materials rules at 49 C.F.R. Parts 171 through 180, and Pele itself stays on the Idaho site, so that analysis remains untested for any production unit.
What Environmental Review Did Project Pele Complete?
Project Pele completed an environmental impact statement under the National Environmental Policy Act, 42 U.S.C. § 4332(2)(C), with a final statement in February 2022 and a Record of Decision in April 2022.
The Strategic Capabilities Office issued its Notice of Intent in March 2020, took public comment, and published the final statement before choosing to proceed. The Record of Decision selected Idaho National Laboratory as the demonstration site and authorized the office to build and demonstrate the prototype. Follow on units at other installations will require their own site specific environmental review.
How Does Executive Order 14299 Change the Pele Timeline?
Executive Order 14299, signed in May 2025 and published at Federal Register volume 90, number 102, sets September 30, 2028 as the deadline for an Army regulated reactor on a domestic military installation under Section 3(a).
Pele operates under Department of Energy authorization, and the Section 3(a) reactor must be regulated by the Army, so the two obligations differ in regulator and site. Section 3(d) requires the Secretary of Defense to submit recommendations within 240 days on legislative and regulatory actions covering the distribution, operation, replacement, and removal of advanced reactors and spent nuclear fuel on military installations. Section 5(b) directs the Secretary of Energy to release not less than 20 metric tons of high assay low enriched uranium into a fuel bank for qualifying private projects, and Section 5(c) directs both Secretaries to authorize privately funded fuel recycling, reprocessing, and fabrication at their sites. Each provision touches the supply chain that follow on Pele style reactors need.
What Liability Rules Apply to a Department of Energy Authorized Reactor?
Section 170d of the Atomic Energy Act, 42 U.S.C. § 2210(d), authorizes the Secretary of Energy to indemnify contractors against public liability arising from nuclear incidents in the course of contract activities.
The terms of any indemnification agreement for Pele do not appear in the public record I reviewed. Investors and insurers evaluating a commercial derivative of Pele should obtain the contractor indemnity terms and compare them with the Price Anderson coverage that applies to Nuclear Regulatory Commission licensees, because a commercial licensee pays into a secondary financial protection pool and a Department of Energy contractor relies on the indemnity agreement.
Want more industry insights? I publish daily analysis on the intersection of deep tech and venture law.
Open Questions
When will the Department of Energy finish the final safety review and authorize fueled operation? The public record gives 2027 for formal testing and 2028 for electricity, and neither date has a published safety review completion behind it. A further slip pushes the demonstration against the September 30, 2028 date in Executive Order 14299.
Which agency will regulate the follow on Army reactor? Section 3(d) recommendations were due within 240 days of the order, in January 2026, and the public record contains no rulemaking or statutory change that establishes an Army regulator for a reactor at Fort Campbell. The answer sets the compliance cost for every contractor bidding on installation reactors.
How will a fueled reactor move on public roads? The transportation analysis led by Pacific Northwest National Laboratory is a paper study that the Nuclear Regulatory Commission reviewed through its Advisory Committee on Reactor Safeguards, and Pele itself stays at Idaho. No fueled mobile microreactor has yet traveled a public highway under a Department of Transportation permit.
Where will TRISO fuel for production units come from? BWXT proposed a $500 million TRISO fuel plant in Gillette, Wyoming with a 2030 in service target, and a $100 million state grant was recommended to support siting. The 20 metric ton fuel bank in Section 5(b) of the executive order supplies uranium, and the fabrication capacity remains a proposal.
What does a production unit cost? The $7,610 per megawatt hour prototype figure includes development, and a published unit price would let utilities and base commanders compare Pele against diesel generation. No such price has been released.
What happens to the prototype and its fuel after the three year run? The program has no stated plans to move the prototype off the Idaho site, and Section 3(d) of the executive order addresses spent fuel on military installations without naming a disposal path.
Source List
Primary Nuclear and Government Sources
BWX Technologies, Project Pele program page, accessed October 10, 2026. Supplies the company’s milestone record from the June 2022 award through core stacking in June 2026, plus design, fuel, and transport claims.
BWX Technologies, Project Pele Begins Taking Shape with Start of Core Manufacturing, press release, July 24, 2025. Confirms the start of core fabrication at the Lynchburg campus.
The White House, Deploying Advanced Nuclear Reactor Technologies for National Security, Executive Order 14299, May 2025. States the Army reactor deadline of September 30, 2028 and the fuel provisions in Sections 3, 4, and 5.
Primary Legal Sources
Atomic Energy Act of 1954, Section 110, 42 U.S.C. § 2140. Contains the licensing exclusions for Commission contract facilities in subsection (a) and for military utilization facilities in subsection (b).
Atomic Energy Act of 1954, Section 170d, 42 U.S.C. § 2210(d). Authorizes Department of Energy indemnification of contractors against public liability.
National Environmental Policy Act of 1969, 42 U.S.C. § 4332(2)(C). Requires the environmental impact statement completed for Pele in 2022.
Nuclear Safety Management, 10 C.F.R. Part 830, Subpart B. Requires a documented safety analysis for Department of Energy nuclear facilities.
Hazardous Materials Regulations, 49 C.F.R. Parts 171 through 180. Govern the highway transport of radioactive materials.
Executive Order 14299, Federal Register, volume 90, number 102, May 29, 2025. Provides the publication record for the order.
Secondary Nuclear Sources
American Nuclear Society, Nuclear Newswire, Project Pele Progress: BWXT Delivers Fuel to INL, December 4, 2025. Source for the November 5, 2025 delivery of 40,000 compacts, the August 2023 target, and the 2027 and 2028 dates.
American Nuclear Society, Nuclear Newswire, BWXT Starts Building Pele Microreactor Core, August 3, 2025. Dates the start of core fabrication.
American Nuclear Society, Nuclear Newswire, BWXT Wins Project Pele Contract to Supply Nation’s First Microreactor, June 9, 2022. Source for the reported $300 million award value and the two year delivery period.
POWER, Project Pele, DOD’s HTGR Mobile Nuclear Microreactor, Breaks Ground, September 25, 2024. Source for the September 24, 2024 start of site construction, the four container configuration, and the Department of Energy authorization path.
POWER, A First for Military Nuclear Power: TRISO Fuel Arrives at Project Pele, 2025. Source for the 40,000 compact delivery, the program timeline, and the proposed Wyoming TRISO plant.
World Nuclear News, Project Pele Mobile Microreactor to Go Ahead, April 14, 2022. Source for the final environmental impact statement, the Record of Decision, and the fuel source.
Reputable News Sources
Axios, Piecing Together the Pele Power Puzzle, September 30, 2026. Source for the 2026 build status, the three year Idaho operating plan, and the BANR reactor at Fort Campbell.
Bibliography
10 C.F.R. pt. 830, subpt. B (Nuclear Safety Management).
42 U.S.C. § 2140 (Atomic Energy Act § 110).
42 U.S.C. § 2210(d) (Atomic Energy Act § 170d).
42 U.S.C. § 4332(2)(C) (National Environmental Policy Act).
49 C.F.R. pts. 171 to 180 (Hazardous Materials Regulations).
American Nuclear Society. “BWXT Starts Building Pele Microreactor Core.” Nuclear Newswire, August 3, 2025.
American Nuclear Society. “BWXT Wins Project Pele Contract to Supply Nation’s First Microreactor.” Nuclear Newswire, June 9, 2022.
American Nuclear Society. “Project Pele Progress: BWXT Delivers Fuel to INL.” Nuclear Newswire, December 4, 2025.
Axios. “Piecing Together the Pele Power Puzzle.” September 30, 2026.
BWX Technologies. “Project Pele Begins Taking Shape with Start of Core Manufacturing.” Press release, July 24, 2025.
BWX Technologies. “Project Pele.” Program page. Accessed October 10, 2026.
Exec. Order No. 14299, Deploying Advanced Nuclear Reactor Technologies for National Security, 90 Fed. Reg. no. 102 (May 29, 2025).
POWER. “A First for Military Nuclear Power: TRISO Fuel Arrives at Project Pele.” 2025.
POWER. “Project Pele, DOD’s HTGR Mobile Nuclear Microreactor, Breaks Ground.” September 25, 2024.
The White House. “Deploying Advanced Nuclear Reactor Technologies for National Security.” Presidential action, May 2025.
World Nuclear News. “Project Pele Mobile Microreactor to Go Ahead.” April 14, 2022.