What NASA’s Only Nuclear Reactor Teaches Reactor Developers
Executive Summary
The Plum Brook Reactor Facility, NASA’s only nuclear reactor, cost $15 million to build in Ohio and about $230 million to decommission before the NRC terminated its licenses in 2012.
NASA built the 60 megawatt Plum Brook Reactor near Sandusky, Ohio, to irradiate materials for the nuclear aircraft program and then the nuclear rocket program. It reached criticality on June 14, 1961, accumulated about 98,000 megawatt days of operation, and shut down permanently in January 1973. The Nuclear Regulatory Commission terminated Facility Licenses TR 3 and R 93 on October 10, 2012, after the licensee completed final status surveys across an 11 hectare site.
The customer programs ended before the reactor did. The nuclear airplane was cancelled in 1961 and the nuclear rocket program ended as Apollo closed, so the facility entered a possession only license status that lasted about 25 years. Decommissioning then consumed a projected $230 million in nominal dollars, more than fifteen times the construction cost. The largest costs came from more than 7,000 meters of buried piping, seven hot cells, and a reactor vessel whose core region held an estimated 1.1 quadrillion becquerels.
Four practices held the final bill down: a dose analysis that redirected the cutting plan before work began, a mockup reactor used for crew training, detailed shutdown records, and a small trial cleanup that tested the hot cell method before NASA committed to it. The legal record runs through 10 CFR 50.82, the unrestricted release standard in 10 CFR 20.1402, and the Price Anderson Act of 1957, which now governs liability for the commercial reactors that follow this one.
Detailed Findings
What Was the Plum Brook Reactor Facility and Why Did NASA Build It?
The Plum Brook Reactor Facility was a 60 megawatt, water cooled and water moderated materials test reactor that NASA operated near Sandusky, Ohio, about 50 miles west of its Lewis Research Center, now the Glenn Research Center. The National Advisory Committee for Aeronautics bought the land in 1956 and planned the reactor for the nuclear aircraft program. After the nuclear airplane was cancelled in 1961, the same reactor served the nuclear rocket program and studies of power systems for spacecraft. NASA describes it as the only nuclear facility the agency ever built.
Published accounts date the start of site work to September 1956 and the start of construction to 1958. NASA’s own history records a construction cost of $15 million and a construction period of about five years to first criticality. The pressure tank sat inside a steel containment vessel designed to prevent release of radioactivity in an accident, a design choice driven by the nearby population of Sandusky.
A companion reactor, the Plum Brook Mockup Reactor, was a 100 kilowatt swimming pool type unit. It received its Atomic Energy Commission license in 1963 and first reached criticality on September 10, 1963. Engineers used it to measure flux and reactivity for experiments, which kept the 60 megawatt reactor free for irradiation work.
How Did the Reactor Operate Between 1961 and 1973?
The reactor reached first criticality on June 14, 1961, and completed its first experimental cycle on August 15, 1963. It offered 44 in core test positions, six horizontal beam holes, and two horizontal holes, which let operators irradiate many samples at once, frequently in small capsules called rabbits. A hot laboratory with seven interconnected hot cells became fully operational in December 1963 for post irradiation examination.
NASA reports more than 70 experiments, most of them studies of radiation effects on materials. Across about ten years the plant accumulated roughly 98,000 megawatt days. The agency’s own accounts differ on the year of full power, giving 1962 in one history and 1963 in a decommissioning paper, and this report does not resolve that difference.
Why Did NASA Shut Down Plum Brook in 1973?
NASA shut down Plum Brook because its customer program ended. The nuclear airplane was cancelled in 1961, and the nuclear rocket program followed as the agency moved toward projects with nearer payoffs such as the Shuttle program. NASA’s history records that the order to shut the reactor came about two weeks after the last Apollo mission. A federal summary places the permanent shutdown on January 5, 1973.
The shutdown itself was orderly. Staff organized into system based teams moved the plant from operation to safe shutdown in about six months. Used and new fuel went back to the supplier. Operators drained and washed down the 8 meter deep quadrant and canal system and drained all piping. They kept the reactor pressure vessel under a dry nitrogen purge with a real time tritium monitor on the exhaust, installed to detect any fracture of the brittle beryllium reflector plates. The teams kept detailed records, and decades later those records told planners that laboratory hoods had been cleaned, which removed picric acid from the list of disassembly hazards.
As a nuclear trained submarine officer aboard USS William H. Bates, I learned that the log is the memory of the plant. The Plum Brook teams applied that discipline in 1973, and their records reduced hazard identification work for crews who arrived 30 years later. The facility then stood in standby under a possess but do not operate license for nearly 25 years.
How Did NASA Decommission Plum Brook Between 1999 and 2012?
NASA decommissioned Plum Brook by decontaminating the site to unrestricted release levels and demolishing structures to one meter below grade, with preparatory work beginning in 1999 and license termination in 2012. NASA submitted its decommissioning plan under 10 CFR 50.82(b) on December 20, 1999. The NRC published its environmental assessment and finding of no significant impact on March 28, 2000, and approved the plan on March 20, 2002, through Amendment 11 to License TR 3 and Amendment 7 to License R 93.
NASA submitted a revised final status survey plan in 2007, and the NRC approved it on March 24, 2008. NASA requested license termination on September 18, 2012, supported by a Final Status Survey Report with one summary and eighteen attachments. The NRC verified that the criteria of the approved plan were met, concluded that the facility and site qualify for unrestricted release under 10 CFR 20.1402, and terminated both licenses under 10 CFR 50.82(b)(6). The Federal Register notice carries the signature date of October 10, 2012.
The decommissioning team projected a total cost near $230 million over about 12 years. A later published tally gives $253 million. The sources reviewed for this report do not reconcile the two figures, so this report treats the projection as the lower estimate and the later tally as the higher estimate, both in nominal dollars.
The project recorded about 1.9 million person hours, two minor lost time accidents, and no detectable releases to the environment. Total worker dose came to 0.33 person sievert against a plan estimate of 0.69 person sievert.
What Did the Reactor Vessel Segmentation Teach Planners About Dose?
Dry segmentation of the reactor vessel held worker dose to about one fifth of what the original platform plan projected, and the better plan appeared only after planners completed a dose analysis they had skipped. The vessel stood 12 meters tall and 3 meters in diameter, with its core 7 meters below grade and its control rod drives in a room 18 meters below grade. Walls of 2.5 to 7.5 centimeters of carbon steel with a welded stainless steel liner sat inside a high density concrete bioshield 0.6 to 2.6 meters thick. The core and vessel held an estimated 1.1 quadrillion becquerels, an estimate later found conservative.
The open vessel measured 11.0 millisieverts per hour at its top. The shielded work platform that planners first chose would have left 0.5 millisieverts per hour at the work position, a level judged too high under the ALARA principle. The replacement used three nested shrapnel shields of 18 metric tons each, built from 20 centimeter carbon steel, and brought the general area dose rate down to 20 microsieverts per hour. Crews worked with 8 meter poles, jib cranes, in tank cameras, and a milling machine on a track. They removed the beryllium reflector plates with custom disposable clamps and shipped them in containers filled with epoxy to absorb shock, contain tritium, and shield.
The campaign ran just over one year and removed 36 metric tons of steel and aluminum carrying 370 trillion becquerels. The hottest single item, a control rod section, read 16 millisieverts per hour on contact. Total work dose was 127 millisieverts. Crews rehearsed tooling and procedures on the Mockup Reactor, where the highest contact dose was 0.02 millisieverts per hour. A 2.5 centimeter asbestos layer between the vessel and the bioshield required repeated remediation, which added time without adding technical difficulty.
How Did Hot Cells and Buried Piping Drive the Decommissioning Cost?
Hot cells and buried piping drove the cost because both held contamination in places that the records described poorly. The seven hot cells covered 77.3 square meters, and the largest was licensed for 55.5 quadrillion becquerels. Contamination in the cells was 53 percent cesium 137, 33 percent strontium 90, 11 percent tritium, and 3 percent cobalt 60. In 2005 the project weighed a rip and ship approach, which demolishes and disposes of everything, against decontaminating to release levels and then demolishing. Studies found little cost difference, and the main unknown was the disposal cost of about 2,268,000 kilograms of contaminated concrete.
NASA tested the decision on Hot Cell 1, about 40 percent of total cell area and the most contaminated. Decontaminating it cost $1 million less than the rip and ship estimate, and the chosen approach avoided about 2.3 million kilograms of radioactive waste. The cell windows, each 1.3 meters thick, failed the toxicity characteristic leaching test and went out as mixed waste. Roof slabs of about 20 metric tons each were decontaminated by sponge blasting and released.
Piping created the larger planning problem. The site held more than 7,000 meters of plant piping reaching 17 meters below grade, with diameters from 2 centimeters to 0.8 meters, and about 1,200 meters of storm drains. The project paper identifies the little attention given to below grade piping in the first three years as a significant planning oversight, and it reports that as built drawings, especially for floor drains, proved unreliable. Cleaning and surveying pipe in place with a vacuum assisted flail cleaner cost about $75 to $125 per foot, while excavating pipe after a concrete cutout cost about $350 per foot. The in place approach carried a projected saving of about $10 million, and the project grouted about 2,500 meters of larger piping before license termination.
Soil added a third stream. Crews shipped about 4,536 metric tons to a disposal site in Clive, Utah, sent about 9,072 metric tons to a Tennessee disposal program at less than half the Utah cost, and assayed about 42,600 metric tons for reuse as onsite backfill using a sorting system that handled up to 1,100 metric tons in a 10 hour day. Cesium 137 found along Plum Brook creek off the site in August 2005 led to an ALARA cleanup by hand crews in summer 2010. NASA credits early community outreach with building the trust that carried the project through that event.
The standby years carried their own cost. A 2015 audit by the NASA Office of Inspector General reported that the reactor building carried deferred maintenance of about $12.86 million before demolition, and that NASA had demolished or excessed 18 Plum Brook structures since October 2011, removing about $138.9 million of current replacement value.
What Does Plum Brook Teach Modern Reactor Developers?
Plum Brook teaches modern developers that the exit bill belongs in the first financial model. A $15 million facility produced a projected $230 million obligation after its only customers left, and NASA carried the difference as a project cost. A commercial developer holding a stranded test reactor has no agency budget behind it, which is why 10 CFR 50.75 requires decommissioning funding assurance from licensees.
Dose analysis belongs before the work plan, as the platform redesign shows. A mockup reactor belongs in the training plan, as the Mockup Reactor showed on a unit with a highest contact dose of 0.02 millisieverts per hour. Shutdown records belong in the operating routine, and as built drawings of embedded and buried systems belong in the permanent record, since the floor drain drawings failed the people who needed them. A small trial of the chosen method, as Hot Cell 1 provided, converts a cost argument into evidence.
The lessons apply to current programs. In 2025 the administration moved to a plan for a commercially built lunar fission reactor ready for launch by 2030. NASA demolished the only reactor it ever built, so any irradiation testing for that program will occur at facilities that other organizations own.
Legal and Regulatory Implications
The Atomic Energy Commission licensed Plum Brook as a test reactor under the Atomic Energy Act of 1954, and the licenses carry the TR prefix. Licensing authority passed to the NRC in 1975 under the Energy Reorganization Act of 1974, 42 U.S.C. 5801 and following. NASA held Facility License TR 3 for the 60 megawatt reactor and Facility License R 93 for the Mockup Reactor, under NRC Docket Numbers 50 30 and 50 185.
The decommissioning rule is 10 CFR 50.82. Subsection (a)(3) requires decommissioning to finish within 60 years of permanent cessation of operations, and Plum Brook finished in 39 years after its 1973 shutdown. Licensees that had ceased operations before the 1996 decommissioning rule, as NASA had, proceeded under subsection (b) with a decommissioning plan, and the NRC terminated the licenses under subsection (b)(6). The environmental review followed 10 CFR Part 51, and the NRC issued a finding of no significant impact on March 28, 2000.
The cleanup standard is the radiological criteria for unrestricted use in 10 CFR 20.1402, part of Subpart E of 10 CFR Part 20, which sets a limit of 25 millirem per year total effective dose equivalent above background plus a requirement to keep doses as low as reasonably achievable. NASA set derived concentration guideline levels with the RESRAD and RESRAD Build codes, and one soil surrogate level for cesium 137 was 0.54 becquerels per gram.
Liability for commercial reactors rests on Section 170 of the Atomic Energy Act, 42 U.S.C. 2210, the Price Anderson Act, first enacted in 1957 while Plum Brook was under construction. Plum Brook was a federal research reactor, so a commercial developer cannot rely on its experience for the liability analysis. A commercial developer reads Section 170 for the financial protection and indemnity structure that governs the operating life of its reactor, and reads 10 CFR 50.75 and 50.82 for the exit.
The sources reviewed describe the Plum Brook exit as a NASA project cost and do not describe a segregated decommissioning fund comparable to the funding assurance 10 CFR 50.75 now requires. This report did not review the NRC rulemaking for advanced reactor licensing under 10 CFR Part 53, and a developer should confirm how that rule treats decommissioning planning for test reactors, microreactors, and spacecraft reactors before relying on the Plum Brook precedent.
Want more industry insights? I publish daily analysis on the intersection of deep tech and venture law.
Open Questions
First, which cost figure is correct, $230 million or $253 million? The lower number is the decommissioning team’s own projection from 2011 and the higher number is a later published tally. NASA’s final cost accounting was not among the sources reviewed, so investors who benchmark future exit costs against Plum Brook need that reconciliation.
Second, does the decontaminate then demolish approach beat rip and ship at other sites? The 2005 study found little cost difference, and the deciding variable was the disposal price of about 2,268,000 kilograms of concrete. Disposal prices at a developer’s site set the answer, so each developer needs a local estimate.
Third, how will decommissioning planning apply to test reactors and microreactors under current NRC rules? The sources reviewed confirm the Part 50 obligations that bound Plum Brook, and the treatment of newer designs remains to be checked against the text of any applicable licensing rule.
Fourth, where will reactor fuels and materials for spacecraft receive irradiation testing now that NASA’s only reactor is gone? The 2025 lunar reactor plan sets a 2030 launch target, and the answer determines schedule risk for the commercial companies that will build the hardware.
Fifth, how long do the residual cesium 137 and strontium 90 results on the released site and the Plum Brook creek hold within the unrestricted release limit? The NRC verified the criteria in 2012, and no later survey was among the sources reviewed.
Source List
Primary nuclear and government sources, most authoritative first.
1. Nuclear Regulatory Commission, Termination of Facility Licenses for the Plum Brook Reactor Facility, Federal Register, Volume 77, Number 201, October 17, 2012, available at govinfo.gov. This notice records the license amendments, the dates, the Final Status Survey Report structure, and the termination under 10 CFR 50.82(b)(6).
2. Nuclear Regulatory Commission, Notice of the Plum Brook Reactor Facility Decommissioning Plan and Environmental Assessment, Federal Register, March 28, 2000, available at govinfo.gov. This notice describes the 11 hectare site, the possession only status, and the December 20, 1999 submission.
3. NASA History Division, Plum Brook Station history, NASA SP 4533, accessed October 10, 2026, available at nasa.gov. This history supplies the $15 million construction cost, the criticality date, the experiment facilities, and the reasons for the 1973 shutdown.
4. Keith M. Peecook, An Overview of the NASA Plum Brook Reactor Facility Decommissioning: Facilities, Proceedings of the Canadian Nuclear Society, September 11, 2011, available through the Canadian Nuclear Society proceedings archive. This paper supplies the vessel, hot cell, dose, and shutdown record details.
5. Keith M. Peecook, Piping, Public Outreach, and Soil Assaying at the NASA Plum Brook Reactor Facility, Proceedings of the Canadian Nuclear Society, September 11, 2011, available through the Canadian Nuclear Society proceedings archive. This paper supplies the piping, soil, cost per foot, and outreach figures.
6. NASA Office of Inspector General, Report IG 15 014, April 23, 2015, available at oig.nasa.gov. This audit supplies the deferred maintenance and demolition figures.
7. NASA, Plum Brook Reactor Facility, Glenn Research Center web page, accessed October 10, 2026, available at nasa.gov. This page confirms the 60 megawatt rating, the more than 70 experiments, and the cause of the 1973 shutdown.
Secondary sources.
8. American Nuclear Society, Nuclear Power on the Moon: What We Are Watching, September 2, 2025, available at ans.org. This article reports the lunar reactor launch target of 2030.
9. Wikipedia, Plum Brook Reactor, accessed October 10, 2026, available at en.wikipedia.org. This page supplies the January 5, 1973 shutdown date and the $253 million decommissioning tally, both treated as secondary and unverified against primary sources.
Bibliography
Legal Sources (Bluebook)
Atomic Energy Act of 1954, 42 U.S.C. §§ 2011 and following.
Energy Reorganization Act of 1974, 42 U.S.C. § 5801 and following.
Price Anderson Act, 42 U.S.C. § 2210 (originally enacted 1957).
10 C.F.R. § 20.1402 (2012); 10 C.F.R. pt. 20, subpt. E.
10 C.F.R. § 50.75 (2012); 10 C.F.R. § 50.82 (2012); 10 C.F.R. pt. 51.
Nuclear Regulatory Commission, Facility License Terminations, NASA Plum Brook Reactor Facility, 77 Fed. Reg. (Oct. 17, 2012) (Vol. 77, No. 201).
Nuclear Regulatory Commission, Environmental Assessment and Finding of No Significant Impact, NASA Plum Brook Reactor Facility, 65 Fed. Reg. 16421 (Mar. 28, 2000).
Non Legal Sources (Chicago)
American Nuclear Society. Nuclear Power on the Moon: What We Are Watching. September 2, 2025. ans.org.
National Aeronautics and Space Administration. Plum Brook Reactor Facility. Glenn Research Center. Accessed October 10, 2026. nasa.gov.
National Aeronautics and Space Administration. Plum Brook Station History. NASA SP 4533. NASA History Division. Accessed October 10, 2026. nasa.gov.
NASA Office of Inspector General. Report IG 15 014. April 23, 2015. oig.nasa.gov.
Peecook, Keith M. An Overview of the NASA Plum Brook Reactor Facility Decommissioning: Facilities. Proceedings of the Canadian Nuclear Society, September 11, 2011.
Peecook, Keith M. Piping, Public Outreach, and Soil Assaying at the NASA Plum Brook Reactor Facility. Proceedings of the Canadian Nuclear Society, September 11, 2011.
Wikipedia. Plum Brook Reactor. Accessed October 10, 2026. en.wikipedia.org.