Four New Reactors Reached Criticality in America in 2026

New U.S. Reactor Designs: Development Progress, Timelines, and Power Output

Executive Summary

Four new U.S. reactor designs achieved criticality between June 4 and July 4, 2026, at Idaho National Laboratory, the first American reactor licensing milestones since 1973. Antares Nuclear’s Mark 0, Valar Atomics’ Ward 250, Deployable Energy’s Unity, and Aalo Atomics’ test reactor each sustained a nuclear chain reaction inside a structure small enough to ship in a standard cargo container, at electric outputs ranging from about one megawatt to twenty megawatts. Three additional designs, including Oklo’s Aurora Powerhouse and Radiant Nuclear’s Kaleidos, are approaching the same milestone at the same laboratory complex, and the Department of Energy’s Secretary indicated in June 2026 that up to four more prototypes could reach criticality before year end.

The surge follows four executive orders signed by the president in May 2025 that direct the Nuclear Regulatory Commission to complete license reviews within eighteen months, call for licensing ten new reactors by 2030, and set a goal of quadrupling the nation’s nuclear capacity by 2050. The 2024 ADVANCE Act already cut the Commission’s hourly fee for advanced reactor applicants by more than half, from 318 dollars to 148 dollars, and created financial prizes for the first reactors licensed under the Commission’s newer review process. At the same time, the Department of Energy’s Reactor Pilot Program is funding criticality demonstrations for nine developers at national laboratory sites, while separate applicants including TerraPower, Kairos Power, and X energy are advancing larger reactors of 75 to 345 megawatts through full Commission licensing.

For energy investors and utility executives, the practical distinction is between a reactor that has reached criticality under Department of Energy authorization on federal land and a reactor licensed by the Commission to sell power commercially off site. Nearly every design described in this report still needs the latter before it can operate as a revenue generating power plant.

Detailed Findings

What development progress have new U.S. reactor designs made in 2026

Idaho National Laboratory, an 890 square mile stretch of high desert west of Idaho Falls, Idaho, hosted four consecutive criticality events in less than a month during the summer of 2026. Antares Nuclear, a company founded in 2023 and based in Torrance, California, brought its Mark 0 reactor critical at 12:30 a.m. on June 4, 2026, inside a repurposed sodium waste treatment building at the laboratory’s Materials and Fuels Complex. The event marked the first new reactor design to reach criticality in the United States since 1973 and the first non light water design licensed domestically in that span. Valar Atomics followed on June 18, 2026, when its Ward 250 reactor achieved criticality at the San Rafael Energy Lab in Emery County, Utah, the only one of the four events to occur outside the Idaho laboratory. Deployable Energy, incorporated in 2025, brought its Unity reactor critical at 11:55 p.m. on June 30, 2026, after building a 340,000 square foot structure at the Idaho site in roughly 150 days. Aalo Atomics, based in Austin, Texas, reached criticality with its Aalo X test reactor twenty minutes into July 4, 2026, a date that matches the target the president’s May 2025 executive orders set for the Department of Energy’s Reactor Pilot Program to demonstrate criticality in at least three advanced reactors outside the national laboratory system.

Two more designs are close behind. Radiant Nuclear’s one megawatt Kaleidos reactor is undergoing component testing inside the Demonstration of Microreactor Experiments facility, a repurposed test bed at the Materials and Fuels Complex that reopened to developers in April 2026 on the site of the retired Experimental Breeder Reactor II. Oklo has excavated a seventy five foot deep pit at the same complex for its Aurora Powerhouse Project, removing more than 100,000 cubic yards of rock and drilling 20,000 boreholes since February 2026 in preparation for concrete work. Separately, Oklo’s Groves Isotope Test Reactor in Lockhart, Texas, received a substantial completion certification from the Department of Energy in April 2026, clearing the open, water cooled unit to load fuel and reach criticality. Natura Resources’ MSR 1, a one megawatt molten salt reactor planned for Abilene Christian University in Texas, already holds a Commission construction license, making it the second advanced reactor design and the first liquid fueled design ever licensed for construction by the Commission; it remains enrolled in the Reactor Pilot Program to demonstrate criticality.

Larger reactors intended for direct grid connection are progressing through the Commission’s full licensing process rather than the Department of Energy’s pilot authority. TerraPower received a construction permit for its Natrium reactor in Kemmerer, Wyoming, in March 2026, the first the Commission has issued for a commercial reactor that does not use ordinary water as its coolant, and broke ground the following month after the Commission completed its safety review roughly eleven percent under its projected budget. Kairos Power began construction on its Hermes test reactor in Oak Ridge, Tennessee, in May 2025 and broke ground on the follow on Hermes 2 unit in April 2026, though the company has since asked the Commission to extend its construction completion deadline from December 31, 2026, to April 30, 2029. Dow’s application for a construction permit covering an X energy Xe 100 reactor at Seadrift, Texas, remains under Commission review. NuScale Power’s VOYGR design, certified by the Commission in 2023 as the first small modular reactor design ever approved in the United States, has yet to begin construction on a commercial plant.

What is the timeline to full commercial operation for these reactors

Antares Nuclear’s public schedule calls for its next design, the electricity producing Mark 1, to be tested in 2027 and for reactors to be deployed on customer sites in 2028. The company has separate delivery obligations to the U.S. Air Force at Joint Base San Antonio in 2027 and to the U.S. Army by September 2028, and it has tested a 100 kilowatt unit at NASA’s Marshall Space Flight Center in Alabama since 2025 for possible use in space travel and lunar power. Valar Atomics briefly used its Ward 250 reactor to power a website hosted on an Nvidia Blackwell chip on July 1, 2026, and Nvidia has agreed to purchase up to 30 megawatts of electricity from Valar’s Utah facility by the end of the decade to help power a nearby data center complex. Deployable Energy has set a goal of producing 1,000 one megawatt reactors a year by 2030 and 10,000 a year by the mid 2030s, with a target of six months from order to delivery. Aalo Atomics expects to sell its commercial Aalo X reactor at commercial scale in 2027 and to begin assembling Aalo Pod plants, which house up to five ten megawatt reactors, for commercial buyers by 2029.

Oklo anticipates commercial operations at its Aurora Powerhouse Project by 2028, roughly two years after the site work now underway. The company’s separate agreement with Meta, signed in September 2025, calls for an Oklo reactor to power a 200 acre data center campus in Pike County, Ohio, by the early 2030s. Natura Resources plans to complete its full MSR 1 reactor system at Abilene Christian University by 2028 and is simultaneously developing a 100 megawatt commercial design based on the same molten salt technology. Among the larger reactors, TerraPower expects its Kemmerer, Wyoming, Natrium plant to be complete in 2030, the same year it has agreed to begin supplying power under a January 2026 agreement covering eight Natrium plants for Meta. Kairos Power’s Hermes 2 unit is tied to a purchase agreement with Google and the Tennessee Valley Authority for 500 megawatts of power by 2035, even as the underlying Hermes test reactor’s construction deadline has slipped to 2028 or 2029.

What are the technical design and power output specifications of these reactors

The reactors emerging from this cycle of development span two distinct categories. Microreactors, most under 20 megawatts electric, are built in factories, shipped whole or in modules, and sited in below ground chambers measured in tens of feet rather than acres. Small modular reactors and larger advanced designs, ranging from 75 to 345 megawatts electric, require conventional construction permits and multi year site work comparable to a traditional power plant, though at a fraction of the size of the 1,000 megawatt light water reactors built in the twentieth century. The table below summarizes the coolant, fuel, dimensions, and electric output disclosed for each design.

DeveloperReactorCoolant and FuelSizeElectric OutputStatus as of July 2026
Antares NuclearMark 0Sodium heat pipes; high assay low enriched uraniumFits a standard shipping container in a 26 foot chamberUp to 20 megawattsAchieved criticality June 4, 2026
Valar AtomicsWard 250Helium cooled; TRISO fuel75 feet long, 15 feet wide, about 120 tonsUp to 5 megawattsAchieved criticality June 18, 2026
Deployable EnergyUnityHelium cooled and water moderated; standard low enriched uranium20 foot shipping container core; 696 fuel rods in 63 gallons of waterAbout 1 megawattAchieved criticality June 30, 2026
Aalo AtomicsAalo X test reactorFuel enriched to 4.95 percent20 feet tall, 10 feet wide10 megawatts per unitAchieved criticality July 4, 2026
Radiant NuclearKaleidosComponent level testing ongoingFits a 20 foot shipping container1 megawattApproaching criticality; 150 hour demonstration planned for summer 2026
OkloAurora PowerhouseSodium cooled fast fissionBuilt on site at Idaho National Laboratory75 megawatts; runs about a decade without refuelingUnder construction; commercial operations targeted 2028
OkloGroves Isotope Test ReactorOpen, water cooled; produces medical and defense isotopesLockhart, TexasNot a power reactorSubstantial completion certified April 2026; awaiting fuel load
Natura ResourcesMSR 1Molten salt; uranium tetrafluoride dissolved in saltAbilene Christian University, Texas1 megawattCommission construction license issued; criticality pending under the Reactor Pilot Program
TerraPowerNatriumSodium cooled fast reactor with molten salt energy storageKemmerer, Wyoming345 megawatts, boostable to 500 megawatts for over 5.5 hoursConstruction permit issued March 2026; completion targeted 2030
Kairos PowerHermes and Hermes 2Molten fluoride salt cooled; non power test unitsOak Ridge, TennesseeTest units, not rated for commercial powerHermes construction since May 2025; Hermes 2 groundbreaking April 2026; completion now targeted 2028 to 2029
X energyXe 100Helium cooled pebble bed, high temperature gas reactorSeadrift, Texas (proposed)About 80 megawatts per unit; 320 megawatts for a four unit plantConstruction permit application under Commission review
NuScale PowerVOYGRLight water, pressurizedModular units combined in plants of four to twelve modulesAbout 77 megawatts per module; 308 to 924 megawatts per plantDesign certified by the Commission in 2023; no plant yet under construction

Legal and Regulatory Implications

Reaching criticality under the Reactor Pilot Program does not, by itself, authorize a developer to sell electricity. The program operates under the Department of Energy’s own authority under the Atomic Energy Act of 1954 to build and test reactors on federal land, an authority separate from the license the Nuclear Regulatory Commission issues to a private company that wants to generate power for commercial sale. A developer that wants to operate a power reactor off federal property still needs a Commission license, either a two step construction permit and operating license under Part 50 of Title 10 of the Code of Federal Regulations or a combined license under Part 52. Every microreactor described in this report that has reached criticality at Idaho National Laboratory or the San Rafael Energy Lab has done so under Department of Energy authorization; none yet holds a Commission license to sell power commercially.

The 2024 ADVANCE Act, formally the Accelerating Deployment of Versatile, Advanced Nuclear for Clean Energy Act, changed the economics of that licensing path. Section 201 of the Act required the Commission to charge advanced reactor applicants a reduced hourly rate that covers only the portion of the agency’s budget spent on staff salaries and benefits rather than its full overhead; the Commission’s fiscal year 2025 fee rule set that rate at 148 dollars an hour, versus 318 dollars for a conventional applicant, effective October 1, 2025. The Act also created five prizes that offset an applicant’s regulatory fees, including one reserved for the first reactor licensed under the Part 52 combined license process, and it directed the Commission to develop procedures for siting reactors on brownfield sites such as retired coal plants.

Four executive orders signed by the president on May 23, 2025, went further, directing the Commission to complete license reviews within eighteen months and to revise its regulations and guidance within nine to eighteen months of the order. A companion order directed the Secretary of Energy to establish the Reactor Pilot Program with an explicit goal, later met by Aalo Atomics, of demonstrating criticality in at least three advanced reactors outside the national laboratory system by July 4, 2026. The orders also set policy goals of licensing ten new reactors by 2030 and quadrupling national nuclear capacity by 2050, though neither goal carries an enforceable deadline against private developers.

Every commercial reactor eventually built from these designs will need to address liability coverage under the Price Anderson Nuclear Industries Indemnity Act, which pools private insurance and industry funded retrospective premiums to cover the cost of a nuclear incident and caps aggregate liability at a level the Commission adjusts periodically. Test reactors operating on Department of Energy property are indemnified instead under the department’s own contract authority; developers will need to transition to Price Anderson Act coverage, or negotiate an equivalent Department of Energy indemnification agreement, before any of these designs can operate commercially off federal land.

Want more industry insights? I publish daily analysis on the intersection of deep tech and venture law.

Subscribe to The Innovation Attorney on Substack

Open Questions

Will the Nuclear Regulatory Commission grant Antares Nuclear, Valar Atomics, Deployable Energy, and Aalo Atomics a commercial license before their Department of Energy pilot authorizations expire, and on what timetable will each company file its application.

Can Kairos Power complete construction of the Hermes test reactor by its newly proposed April 2029 deadline after missing the original 2026 target, and what does that slippage suggest about Hermes 2’s ability to meet the 2035 delivery date in its Google and Tennessee Valley Authority agreement.

How will the domestic supply of high assay low enriched uranium and TRISO fuel keep pace with demand once Antares, Valar, Aalo, and Radiant move from single test units to the production volumes their executives have described, some as high as 10,000 reactors a year.

What level of aggregate liability coverage will the Commission require under the Price Anderson Act for a fleet of one to twenty megawatt reactors that a single utility or data center operator might deploy in groups, rather than the single large reactor the Act’s premium structure was built around.

Will the Commission’s eighteen month review deadline, ordered in May 2025, survive contact with an application as technically novel as TerraPower’s sodium cooled Natrium design or Kairos Power’s molten salt cooled Hermes design, both of which lack a direct licensing precedent.

How will Oklo’s Aurora Powerhouse Project, built on public land at Idaho National Laboratory, obtain a Commission license to sell power to a private customer such as Meta once construction is complete, given that its sibling isotope reactor in Lockhart, Texas, was built as a private civil construction project on private land.

Will the reduced advanced reactor fee rate under Section 201 of the ADVANCE Act remain in place long enough to matter for developers whose applications will not reach the Commission for another two to three years.

Source List

Federal Register. Reforming Nuclear Reactor Testing at the Department of Energy, document number 2025-09799, published May 29, 2025. Primary text of the executive order directive establishing the Reactor Pilot Program and its criticality target.

U.S. Nuclear Regulatory Commission. Hermes, Kairos Power Application docket. nrc.gov. Official licensing status for the Hermes and Hermes 2 test reactors.

U.S. Nuclear Regulatory Commission. About the ADVANCE Act and Licensing Efficiencies. nrc.gov. Agency summary of Section 201 fee changes and the Part 52 prize structure.

U.S. Department of Energy, Office of Nuclear Energy. Fact sheet on the May 2025 nuclear energy executive orders. energy.gov, June 2025. Agency summary of the policy goals and Reactor Pilot Program mandate.

U.S. Department of Energy, Office of Nuclear Energy. One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing. energy.gov. Progress update on the pilot program and the Demonstration of Microreactor Experiments test bed.

U.S. Energy Information Administration. U.S. Nuclear Industry. eia.gov/energyexplained/nuclear/us-nuclear-industry.php. Baseline statistics on the existing 96 reactor fleet and its share of national electricity generation.

TerraPower. NRC Approves the Natrium Reactor Construction Permit. terrapower.com, March 2026. Construction permit and Kemmerer, Wyoming site details for the Natrium reactor.

X energy. Xe 100: High Temperature Gas Cooled Nuclear Reactors. x-energy.com. Technical specifications for the Xe 100 pebble bed reactor.

NuScale Power. VOYGR small modular reactor technical overview. nuscalepower.com. Module and plant configuration specifications for the VOYGR design.

Nuclear Energy Institute. ADVANCE Act of 2024 overview. nei.org. Industry summary of the Act’s licensing and fee provisions.

American Nuclear Society. Nuclear Newswire coverage of the Hermes and Natrium construction permits. ans.org. Independent trade press confirmation of licensing milestones.

John Haughey. Inside the Next Gen Nuclear Power Revolution in Idaho’s High Desert. The Epoch Times, July 28, 2026. On site reporting from Idaho National Laboratory providing the criticality timeline and company level detail underlying this report.

Bibliography

American Nuclear Society. “NRC Approves TerraPower Construction Permit” and related Kairos Power coverage. Nuclear Newswire. ans.org.

Federal Register. Reforming Nuclear Reactor Testing at the Department of Energy. Document No. 2025-09799. May 29, 2025. https://www.federalregister.gov/documents/2025/05/29/2025-09799/reforming-nuclear-reactor-testing-at-the-department-of-energy.

Haughey, John. “Inside the Next Gen Nuclear Power Revolution in Idaho’s High Desert.” The Epoch Times, July 28, 2026. https://www.theepochtimes.com/article/inside-the-next-gen-nuclear-power-revolution-in-idahos-high-desert-6062417.

NuScale Power. VOYGR Small Modular Reactor Technical Overview. nuscalepower.com.

Nuclear Energy Institute. ADVANCE Act of 2024 Overview. nei.org.

TerraPower. NRC Approves the Natrium Reactor Construction Permit. March 2026. terrapower.com/NRC-Approves-Natrium-Reactor-Construction-Permit.

U.S. Department of Energy, Office of Nuclear Energy. Fact Sheet on the 2025 Nuclear Energy Executive Orders. energy.gov, June 2025.

U.S. Department of Energy, Office of Nuclear Energy. One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing. energy.gov.

U.S. Energy Information Administration. U.S. Nuclear Industry. eia.gov/energyexplained/nuclear/us-nuclear-industry.php.

U.S. Nuclear Regulatory Commission. About the ADVANCE Act. nrc.gov/about-nrc/governing-laws/advance-act/about-advance-act.

U.S. Nuclear Regulatory Commission. Hermes, Kairos Application. nrc.gov/reactors/non-power/new-facility-licensing/hermes-kairos.

U.S. Nuclear Regulatory Commission. Licensing Efficiencies. nrc.gov/about-nrc/governing-laws/advance-act/licensing-efficiencies.