AI Data Center Grid Interconnection and Large Load Orders
Executive Summary
An AI data center connects to the grid after the FERC orders of June 18, 2026 by meeting its regional operator’s study, deposit, and curtailable service rules. In docket RM26-4, FERC declined to write one national rule. It issued six show cause orders under Section 206 of the Federal Power Act instead, one to each regional transmission organization, and preliminarily defined a large load as a single site of 50 megawatts or more connecting above 69 kilovolts and not part of a colocated arrangement. As of October 11, 2026, none of the six operators has an approved tariff written in response to those orders, and the remaining compliance filings fall due on November 16, 2026.
The queue data explain the urgency. Berkeley Lab counted 2,061 gigawatts of generation and storage seeking interconnection at the end of 2025, and only 13 percent of the capacity requested between 2000 and 2020 reached commercial operation. PJM’s capacity auction for the 2028/2029 delivery year, held July 14, 2026, cleared 6,831 megawatts short of the reliability requirement at the price cap of $325 per megawatt day. At that cap, 100 megawatts of load carries about $11.9 million per year of capacity cost.
Every fast route in the record trades firmness for speed. SPP offers up to seven years of nonfirm service. MISO proposed 90 day reviews for generation that serves a load at the same substation. PJM proposed that new large loads without their own capacity be curtailed before existing customers in an emergency, starting June 1, 2027. Developers and lenders should price curtailment risk and financial security into every site decision now, because the November 16 filings will set the working rules.
Detailed Findings
What Did FERC Order on June 18, 2026?
FERC opened six proceedings on June 18, 2026, one for each of PJM (EL26-67), SPP (EL26-68), NYISO (EL26-69), MISO (EL26-70), CAISO (EL26-71), and ISO New England (EL26-72), reported at 195 FERC ¶ 61,211 through 61,216. Each order preliminarily found the operator’s tariff unjust, unreasonable, or unduly discriminatory because it lacks adequate provisions for large loads. The Commission chose individualized Section 206 proceedings over notice and comment rulemaking, citing speed, regional tailoring, and a fuller evidentiary record.
The orders direct each operator and its transmission owners to address five subjects: transmission service application and study procedures; protections against cost shifting, including a pro forma cost recovery agreement; rates and terms for colocated and behind the meter generation; new transmission services for flexible large loads; and generator interconnection for electrically proximate loads. FERC proposed study timelines of 60 to 90 days and asked operators to give serious consideration to advanced alternative transmission technologies in the near term. PJM and SPP were not ordered to address some items because they had acted in other proceedings.
The procedural calendar ran as follows. Interventions were due July 9, 2026. Informational reports on generation adequacy were due July 20. Requests to hold the case in abeyance for up to 90 days were due August 3, and FERC said it would not grant them reflexively. Show cause responses were due August 17, with interested parties given 30 days to respond. If an abeyance is granted, the revised filing date is November 16, 2026. NYISO and ISO New England filed abeyance motions in August, and the MISO, SPP, and CAISO compliance schedules also run to November.
How Did Docket RM26-4 Begin and What Happened to the Proposed National Rule?
The Secretary of Energy directed FERC on October 23, 2025, under Section 403 of the Department of Energy Organization Act, to consider a rule for large load interconnection, and attached an advance notice of proposed rulemaking in docket RM26-4-000. The notice set out 14 principles. Among them: coverage of new loads above 20 megawatts, including hybrid facilities that share an interconnection point with generation; joint study of load and generation; uniform study deposits, readiness requirements, and withdrawal penalties modeled on the generator process; expedited studies within 60 days for curtailable or dispatchable loads; and full responsibility of the large load for network upgrades assigned through the study. DOE asked for final action by April 30, 2026.
States objected to federal jurisdiction over load interconnection, and many urged FERC to avoid an aggressive assertion that would invite litigation. FERC’s June orders preserve the line between federal and state authority: FERC acts on cost shifting among wholesale transmission customers, and states handle retail cost shifting. The RM26-4 docket remains open for possible later action covering regions outside the six operators, and utilities outside the six operators are encouraged to respond and are under no order to do so.
Which Facilities Count as Large Loads and Who Runs the Study?
A large load in the June orders is a new commercial or industrial customer at a single site with peak demand of at least 50 megawatts, connecting at a voltage above 69 kilovolts, and not part of a colocated arrangement. The figure tracks a proposal from the MISO Large Load Working Group. DOE’s earlier notice used 20 megawatts, and SPP’s accepted High Impact Large Load definition reaches loads above 10 megawatts at 69 kilovolts or below as well as loads above 50 megawatts at higher voltage. PJM’s August 13, 2026 filing also uses 50 megawatts of combined peak demand at a single site, including nearby affiliated facilities.
The study is run by the operator, or by the operator and the transmission owner together, on a request submitted through the load serving entity or utility that will serve the customer. FERC suggested treating facilities within two substations of each other as electrically proximate, and left each operator to define the term for its own grid.
What Steps Does an AI Data Center Follow to Interconnect Now?
The sequence below combines the directives in the June 18 orders with the tariffs already in force in SPP and the filings pending elsewhere. Regional details differ, and every step should be confirmed against the operator’s current tariff.
First, the developer fixes the site, the peak megawatts by phase, the voltage, and the ramp profile, then classifies the load against the operator’s threshold. A request at or above 50 megawatts above 69 kilovolts falls inside FERC’s proposed definition; a request near that line should be sized with the definition in mind, because crossing it triggers registry reporting, readiness deposits, and operational requirements.
Second, the request is filed through the serving utility with the readiness showing the operator requires. FERC asked for rolling applications, readiness milestones, and escalating financial commitments to deter speculative requests. ERCOT, which is outside FERC’s wholesale jurisdiction over this process, shows the practical effect: it excluded 47 projects for failing to submit dynamic model data by July 10, 2026, and 315 more for lacking a qualifying study.
Third, the operator studies the request, with FERC’s stated goal of 60 to 90 days. SPP’s HILL process, effective January 15, 2026 under docket ER26-247-000, and its HILLGA process already study load and generation together. DOE’s notice and FERC’s orders both point toward joint study of a load and the generation built to serve it.
Fourth, the developer chooses a service and a supply plan, described in the next subsection. Fifth, the developer signs a standard agreement that FERC expects to carry telemetry, equipment, and remote disconnect requirements, with SPP’s version including real time telemetry and a ramp limit of 20 megawatts per minute. Sixth, a cost recovery agreement allocates network upgrade costs and posts financial security, and the load joins the operator’s registry or reporting system. Energization follows the completion of upgrades unless a nonfirm or interim service allows earlier operation.
Which Transmission Services Can a Data Center Choose?
FERC’s December 18, 2025 order in the PJM colocation proceeding (docket EL25-49) created the template that the June 18 orders propose for the other operators. It requires three services. Interim nonfirm Network Integration Transmission Service applies while upgrades are built and converts to firm service afterward. Firm contract demand lets a separately metered load that can limit its withdrawals draw a set firm quantity with the same curtailment priority as existing firm service, reserved for at least one year. Nonfirm contract demand allows draws as available during nonemergency conditions up to a set quantity, for terms from one hour to one month, with no firm right to withdraw.
Charges differ by service. All three customer types pay regulation and black start charges on gross demand. Network service and firm contract demand customers pay PJM capacity charges, and nonfirm contract demand customers do not. Withdrawals above reserved amounts draw unreserved use charges. For behind the meter generation, FERC directed PJM to propose a new megawatt threshold limiting how much load a network service customer can offset, with a three year transition for existing customers.
SPP’s Conditional High Impact Large Load Service, accepted by FERC on June 5, 2026 under docket ER26-1323-000 and effective July 1, 2026, is the live version of a nonfirm bridge. A large load receives service using available transmission capacity for up to seven years while upgrades for firm service are built or new generation comes online, and SPP may curtail it during constraints or emergencies. SPP is also developing a Price Adaptive Load Service, with a filing targeted on or before November 16, 2026.
The generation side has its own fast lane. FERC accepted PJM’s Expedited Interconnection Track on June 9, 2026 under docket ER26-1563-000. It applies to generation, not load: projects of at least 250 megawatts able to operate within three years, backed by a state siting authority, limited to 10 requests a year, with a $500,000 study deposit and a $15,000 per megawatt readiness deposit, expiring at the end of 2027. For a 250 megawatt generator those deposits total $4.25 million. A data center developer that pairs with such a project buys speed on the supply side while still needing its own load service.
How Do Cost Allocation and Financial Security Work?
FERC did not change regional wholesale cost allocation. It directed operators to publish network upgrade assignments and costs for large loads on a searchable platform and to report aggregated large load requests by transmission zone, so state regulators can assign retail costs. The pro forma cost recovery agreement runs among the host load serving entity, the transmission owner, and the operator, and requires financial security scaled to the network upgrade cost, which limits stranded asset risk if the load does not materialize. A financial agreement directly between the load and the transmission owner can satisfy the requirement if it protects at least as well.
DOE’s earlier notice would have made the large load fully responsible for assigned network upgrades, with possible crediting mechanisms. The June orders do not adopt that rule for all regions, but the cost recovery agreement pursues the same result by contract. The order text reviewed for this report does not state a security amount, so the figure will come from each operator’s compliance filing.
What Has Happened Since June 18, 2026?
PJM filed on August 13, 2026 in docket ER26-3515-000, proposing an Interim Resource Adequacy Service, a Large Load Registry, and a Bring Your Own New Capacity option. Under the proposal, new loads of 50 megawatts or more entering service after June 1, 2027 without enough new capacity could be curtailed in an emergency before pre emergency load management on existing customers. Loads that bring qualifying new capacity reduce or eliminate that exposure, and the capacity must bid as a price taker in the capacity auction for 10 consecutive delivery years. Loads that reduce under the service could receive up to 50 percent of PJM’s nonperformance charge rate. Starting with the 2029/2030 auction, uncovered incremental large load would be excluded from the demand curve. PJM asked for approval by October 12, 2026.
Responses have been split. A data center trade group asked FERC to reject the proposal or delay it to June 1, 2028, arguing that states cannot opt out and that new loads would subsidize reductions for others. One large technology company argued the service would worsen the capacity shortage and preferred an interruptible service model. A member of Congress supported parts of the plan and asked for partial approval and a public registry. As of this report, no FERC order on the filing has issued.
A related PJM filing, a one time Reliability Backstop Procurement of up to 6,831.3 megawatts with terms up to 15 years and a levelized cost cap of $555 per megawatt day, drew a FERC order on September 29, 2026. The Commission suspended key elements through February 28, 2027 and opened a paper hearing, citing cost allocation to households and small businesses, the rules for a transmission owner leaving PJM, and collateral requirements; one cooperative warned of roughly $2 billion in collateral. PJM’s regular auction for 2029/2030, expected in early December, could face complications.
In MISO, a Zero Injection Generator Interconnection Agreement filing of August 18, 2026 would give 90 day reviews to generation that serves a load at the same substation and voltage, caps generating capacity at the load served, and allows no network upgrades beyond the substation except protection facilities at a neighboring substation. Utilities and clean energy trade groups supported it; environmental and community groups asked FERC to order a rework, citing cost shifting. MISO also planned a Large Load Parallel Study Process filing near the end of September 2026. CAISO has set a compliance filing for November 16, 2026, NYISO targets about March 2027, and ISO New England proposed a bring your own new generation requirement modeled on SPP, with detailed rules in 2027.
How Does ERCOT Differ from the FERC Regulated Regions?
ERCOT operates outside FERC’s wholesale transmission jurisdiction and runs its own process under Texas law. As of July 28, 2026, about 205 gigawatts of large load was eligible for inclusion in ERCOT’s Batch Zero study, with 127 projects eligible as allocated load and 150 as base load. The batch study assigns annual megawatt allocations for 2028 through 2032, sets financial commitment requirements, and produces a transmission plan identifying constraints and upgrades. Senate Bill 6 protects ERCOT’s use of generation units at sites where load is added, for facilities whose generation existed before September 1, 2025. A figure of 198 gigawatts of requests reported for the first quarter of 2026 could not be independently verified in this research.
Where Does Grid Intelligence Enter the Process?
The orders turn interconnection into a data problem. A 60 to 90 day study requires a load model, a ramp profile, a dynamic model, and a curtailment capability that the operator can verify. SPP’s tariff already demands real time telemetry and remote disconnect capability. PJM’s registry would record each large load’s size, location, in service date, backup generation, and fuel type, so operators can locate where reductions are available and states can improve forecasts.
Flexibility has measurable value on the supply side. A Duke University study of 22 balancing authorities serving about 95 percent of peak load found 76 gigawatts of new load could be served at 0.25 percent average annual curtailment, 98 gigawatts at 0.5 percent, and 126 gigawatts at 1.0 percent, with average curtailment events of 1.7 to 2.5 hours. The study did not model transmission congestion, which can reduce the headroom at a specific node. The figures describe a national ceiling for headroom.
FERC’s request that operators consider advanced alternative transmission technologies, such as dynamic line ratings and advanced conductors, adds a second data stream. Vendor claims about capacity gains from those technologies vary by line and weather, and no source reviewed here provides a measured, region wide figure; each claim should be checked against operator study results. The EIA projects U.S. electricity consumption of 4,269 billion kilowatt hours in 2026 and 4,399 billion in 2027, up from a record 4,195 billion in 2025, with commercial sales exceeding residential sales for the first time in 2026.
On a nuclear submarine, every electrical load has a place in a shed order, and the watch team knows it before the casualty occurs. The utility interconnection rules now being written ask a data center to carry a comparable list: which megawatts are firm, which are curtailable, which move to backup generation, and how fast. In my practice, the first document I ask a data center developer for is the study agreement, because the commercial terms depend on it.
What Are the Economics for an Investor or Operator?
The PJM price cap fell 2.5 percent, from $333.44 per megawatt day in the 2027/2028 auction to $325 for 2028/2029. Over 365 days, $325 per megawatt day equals $118,625 per megawatt year, so a 100 megawatt load faces about $11.9 million annually if it pays capacity on gross demand. The backstop procurement cap of $555 per megawatt day equals $202,575 per megawatt year for new capacity. A load that brings its own capacity under PJM’s proposal or under SPP’s service avoids part of that exposure and accepts commitments of 10 delivery years in PJM.
Berkeley Lab data frame the generation side of the bargain: more than five years from request to commercial operation at the median, 75 percent withdrawal for requests submitted from 2000 to 2020, and withdrawal rates above 40 percent even after an interconnection agreement is signed. PJM’s first cycle under its first ready, first served process accepted 715 projects totaling 201.5 gigawatts, including 99.8 gigawatts of gas, 60 gigawatts of storage, and 17.3 gigawatts of nuclear. A developer who depends on a new plant for firm service carries that completion risk, and a lender should ask for the study results before sizing debt.
What Legal and Regulatory Risks Remain for Data Center Developers?
The principal risk is timing. The operators’ filings are due November 16, 2026, comments follow, and FERC orders on those filings are expected after the comment period. Rates, terms, and security amounts for the PJM colocation services remain in a paper hearing. Contracts signed now should address change in tariff terms, curtailment priority, and the allocation of collateral among the developer, the utility, and the supply owner.
Jurisdictional risk persists. States retain authority over retail service and siting, and Pennsylvania’s governor directed state officials on August 18, 2026 to pursue rules that would curtail data centers before other customers in certain emergencies unless the data centers secure incremental capacity, and to tighten permitting for projects above 25 megawatts. A federal tariff that allows nonfirm service does not displace a state rule that requires it.
Litigation risk follows the cost shifting dispute. Comments on PJM’s and MISO’s filings already argue that cost shifts continue, and a rehearing request or court petition could delay effectiveness. A developer should hold both a federal path and a state path in its schedule, and should confirm whether its serving utility is an operator member before assuming a given tariff applies.
Want more industry insights? I publish daily analysis on the intersection of deep tech and venture law.
Open Questions
Will FERC approve PJM’s Interim Resource Adequacy Service, which PJM asked to have approved by October 12, 2026, and with what changes to curtailment priority? The record contains an approval request and sharp opposition. The order will decide whether new loads without their own capacity face emergency curtailment from June 1, 2027, which affects every PJM site decision now in progress.
What financial security amount will operators require in cost recovery agreements? The orders require security scaled to upgrade costs but state no formula. The November 16 filings will supply figures; until then, lenders cannot size collateral or equity reserves with confidence.
How will operators define electrically proximate and colocated loads? FERC suggested two substations, and MISO’s proposal covers one substation while commenters asked for two. The answer sets which developers qualify for a 90 day generation review and which wait in a joint study.
Will the reformed Reliability Backstop Procurement clear FERC before the early December 2029/2030 auction, and who will bear its costs? The suspension runs through February 28, 2027 and the paper hearing has no stated end date. Cost allocation determines whether retail customers or large loads fund up to 6,831.3 megawatts of new capacity.
How much interconnection time does flexibility save? SPP’s seven year nonfirm service and the Duke headroom figures support faster energization, but the Duke study omitted congestion. Operator study data at specific nodes, which a developer can request, would answer the question for each site.
Will FERC extend these rules to regions outside the six operators through the open RM26-4 docket? Many utilities in the Southeast and West sit outside these orders, and a rule there would reach large projects now planned under bilateral utility agreements. The Commission has said the docket remains open.
Source List
FERC, Order Instituting Proceeding Under FPA Section 206, Docket No. EL26-70-000 (MISO), 195 FERC ¶ 61,212. Federal Energy Regulatory Commission. June 18, 2026. Primary text for the 50 megawatt and 69 kilovolt definition, the 60 to 90 day study goal, and the response deadlines. https://www.ferc.gov/sites/default/files/2026-06/EL26-70-000.pdf
Lawrence Berkeley National Laboratory. Queued Up: 2026 Edition, Characteristics of Power Plants Seeking Transmission Interconnection as of the End of 2025. June 2026. Supplies the 2,061 gigawatt queue total, withdrawal rates, and completion rates. https://emp.lbl.gov/news/backlog-power-plants-seeking-transmission-grid-connection-eased-somewhat-2025-amidst
PJM Interconnection. 2028/2029 Base Residual Auction results release. July 14, 2026. Supplies the $325 per megawatt day clearing price, 138,318 megawatts procured, and 6,831 megawatt shortfall. https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2026-releases/20260714-pjm-capacity-auction-procures-138318-mw-of-generation-resources.pdf
PJM Interconnection. Interim Resource Adequacy Service Proposal, fact sheet. August 2026. Describes the registry, curtailment priority, credit, and exclusion from the demand curve. https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/interim-resource-adequacy-service-proposal.pdf
Electric Reliability Council of Texas. Panel presentation on data centers and Batch Zero. August 19, 2026. Supplies the 205 gigawatt Batch Zero eligibility count and exclusions. https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf
Duke University Nicholas Institute. Rethinking Load Growth. February 2025, as reported by POWER Magazine. Supplies the 76, 98, and 126 gigawatt flexibility figures and the congestion caveat. https://www.powermag.com/duke-researchers-grid-flexibility-key-to-accommodate-load-growth
U.S. Energy Information Administration. Short Term Energy Outlook, July 7, 2026, as reported July 8, 2026. Supplies the 2025, 2026, and 2027 consumption figures. https://www.thestar.com.my/tech/tech-news/2026/07/08/us-power-use-to-beat-record-highs-in-2026-and-2027-as-ai-use-surges-eia-says
Day Pitney LLP. FERC Issues Show Cause Orders to Six RTOs/ISOs on Large Load Integration. June 23, 2026. Supplies the docket numbers, citations, five reform categories, and deadline calendar. https://www.daypitney.com/ferc-issues-show-cause-orders-to-six-rtos/isos-on-large-load-integration
Orrick, Herrington and Sutcliffe LLP. FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies. July 2026. Supplies the five directives, the threshold, and the PJM Expedited Interconnection Track deposits. https://www.orrick.com/en/Insights/2026/07/FERC-Show-Cause-Orders-Signal-Broad-Reform-to-Large-Load-Interconnection-Policies
Hunton Andrews Kurth LLP. FERC Show Cause Orders Seek to Accelerate Large Load Interconnections to the Grid. 2026. Supplies the abeyance terms, the jurisdiction discussion, and the open status of RM26-4. https://www.hunton.com/the-nickel-report/ferc-show-cause-orders-seek-to-accelerate-large-load-interconnections-to-the-grid
Mayer Brown LLP. FERC Directs PJM to Facilitate Co Location Arrangements. January 2026. Supplies the three new transmission services and the behind the meter netting terms. https://www.mayerbrown.com/ja/insights/publications/2026/01/ferc-directs-pjm-to-facilitate-co-location-arrangements
Beveridge and Diamond PC. DOE Invokes Rare Authority to Direct FERC to Accelerate Grid Access for Large Loads and Data Centers. October 2025. Supplies the ANOPR principles, the 20 megawatt threshold, and the comment dates. https://www.bdlaw.com/publications/doe-invokes-rare-authority-to-direct-ferc-to-accelerate-grid-access-for-large-loads-and-data-centers/
RMI. Understanding FERC’s Large Load Orders. July 6, 2026. Supplies the SPP definition, the flexible service descriptions, and the cost recovery agreement security structure. https://rmi.org/resources/understanding-fercs-large-load-orders/
Utility Dive. FERC approves PJM fast track review for large generation projects. June 2026. Supplies the Expedited Interconnection Track eligibility, caps, and expiration. https://www.utilitydive.com/news/ferc-pjm-fast-track-expedited-interconnection-eit/822479/
Utility Dive. FERC approves SPP CHILLS large load transmission service. June 8, 2026. Supplies the June 5, 2026 approval and the seven year nonfirm term. https://www.utilitydive.com/news/ferc-spp-chills-large-load-transmission-service/822211/
Utility Dive. MISO zero injection large load filing at FERC. September 9, 2026. Supplies the filing date, the 90 day review, and the support and opposition. https://www.utilitydive.com/news/google-xcel-miso-zero-injection-large-load-ferc/829912/
POWER Magazine. PJM Widens Response to Data Center Load as Capacity Shortfalls Deepen. August 2026. Supplies the docket ER26-3515-000 details, BYONC terms, the backstop procurement filing, and the first cycle queue figures. https://www.powermag.com/pjm-widens-response-to-data-center-load-as-capacity-shortfalls-deepen/
Climate Solutions Law. RTOs and ISOs Answer: A National Preview of How All Six Grid Operators Plan to Respond. July 2026. Supplies the regional compliance plans and dates for SPP, MISO, CAISO, NYISO, and ISO New England. https://www.climatesolutionslaw.com/2026/07/rtos-and-isos-answer-a-national-preview-of-how-all-six-grid-operators-plan-to-respond-to-the-large-load-surge/
ROIC News. PJM data center power auction suspended by federal regulators. September 30, 2026. Supplies the September 29, 2026 FERC suspension through February 28, 2027, with the stated reasons. Single secondary source; verify against the FERC order in the PJM docket. https://www.roic.ai/news/pjms-data-center-power-auction-suspended-by-federal-regulators-09-30-2026
The Dominion Post. PJM’s data center power plan receives mixed reviews. October 2, 2026. Supplies the reactions to the August 13 filing. https://www.dominionpost.com/2026/10/02/pjms-data-center-power-plan-receives-mixed-reviews/
ISO New England and NYISO abeyance motions in Docket Nos. EL26-72-000 and EL26-69-000. August 2026. Confirm that both operators sought abeyance. https://www.iso-ne.com/static-assets/documents/100038/el26-72-000_abeyance.pdf
Bibliography
Technical and Secondary Sources
Beveridge and Diamond PC. 2025. “DOE Invokes Rare Authority to Direct FERC to Accelerate Grid Access for Large Loads and Data Centers.” October. https://www.bdlaw.com/publications/doe-invokes-rare-authority-to-direct-ferc-to-accelerate-grid-access-for-large-loads-and-data-centers/.
Climate Solutions Law. 2026. “RTOs and ISOs Answer: A National Preview of How All Six Grid Operators Plan to Respond to the Large Load Surge.” July. https://www.climatesolutionslaw.com/2026/07/rtos-and-isos-answer-a-national-preview-of-how-all-six-grid-operators-plan-to-respond-to-the-large-load-surge/.
Day Pitney LLP. 2026. “FERC Issues Show Cause Orders to Six RTOs/ISOs on Large Load Integration.” June 23. https://www.daypitney.com/ferc-issues-show-cause-orders-to-six-rtos/isos-on-large-load-integration.
Duke University Nicholas Institute for Energy, Environment and Sustainability. 2025. Rethinking Load Growth. Durham, NC: Duke University. Reported at https://www.powermag.com/duke-researchers-grid-flexibility-key-to-accommodate-load-growth.
Electric Reliability Council of Texas. 2026. “Panel 1: Data Centers.” Presentation to the Texas House Committee on State Affairs, August 19. https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf.
Hunton Andrews Kurth LLP. 2026. “FERC Show Cause Orders Seek to Accelerate Large Load Interconnections to the Grid.” The Nickel Report. https://www.hunton.com/the-nickel-report/ferc-show-cause-orders-seek-to-accelerate-large-load-interconnections-to-the-grid.
ISO New England Inc. and NYISO. 2026. Motions for abeyance, Docket Nos. EL26-72-000 and EL26-69-000. August. https://www.iso-ne.com/static-assets/documents/100038/el26-72-000_abeyance.pdf.
Lawrence Berkeley National Laboratory. 2026. Queued Up: 2026 Edition, Characteristics of Power Plants Seeking Transmission Interconnection as of the End of 2025. Berkeley, CA: Lawrence Berkeley National Laboratory. June. https://emp.lbl.gov/news/backlog-power-plants-seeking-transmission-grid-connection-eased-somewhat-2025-amidst.
Mayer Brown LLP. 2026. “FERC Directs PJM to Facilitate Co Location Arrangements.” January. https://www.mayerbrown.com/ja/insights/publications/2026/01/ferc-directs-pjm-to-facilitate-co-location-arrangements.
Orrick, Herrington and Sutcliffe LLP. 2026. “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies.” July. https://www.orrick.com/en/Insights/2026/07/FERC-Show-Cause-Orders-Signal-Broad-Reform-to-Large-Load-Interconnection-Policies.
PJM Interconnection, L.L.C. 2026. “PJM Capacity Auction Procures 138,318 MW of Generation Resources.” News release, July 14. https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2026-releases/20260714-pjm-capacity-auction-procures-138318-mw-of-generation-resources.pdf.
PJM Interconnection, L.L.C. 2026. Interim Resource Adequacy Service Proposal. Fact sheet, August. https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/interim-resource-adequacy-service-proposal.pdf.
POWER Magazine. 2026. “PJM Widens Response to Data Center Load as Capacity Shortfalls Deepen.” August. https://www.powermag.com/pjm-widens-response-to-data-center-load-as-capacity-shortfalls-deepen/.
RMI. 2026. “Understanding FERC’s Large Load Orders.” July 6. https://rmi.org/resources/understanding-fercs-large-load-orders/.
ROIC News. 2026. “PJM’s Data Center Power Auction Suspended by Federal Regulators.” September 30. https://www.roic.ai/news/pjms-data-center-power-auction-suspended-by-federal-regulators-09-30-2026.
The Dominion Post. 2026. “PJM’s Data Center Power Plan Receives Mixed Reviews.” October 2. https://www.dominionpost.com/2026/10/02/pjms-data-center-power-plan-receives-mixed-reviews/.
U.S. Energy Information Administration. 2026. Short Term Energy Outlook. July 7. As reported July 8, 2026, at https://www.thestar.com.my/tech/tech-news/2026/07/08/us-power-use-to-beat-record-highs-in-2026-and-2027-as-ai-use-surges-eia-says.
Utility Dive. 2026. “FERC Approves PJM Fast Track Review of Large Generation Projects.” June. https://www.utilitydive.com/news/ferc-pjm-fast-track-expedited-interconnection-eit/822479/.
Utility Dive. 2026. “FERC Approves SPP CHILLS Large Load Transmission Service.” June 8. https://www.utilitydive.com/news/ferc-spp-chills-large-load-transmission-service/822211/.
Utility Dive. 2026. “MISO Zero Injection Large Load Filing at FERC.” September 9. https://www.utilitydive.com/news/google-xcel-miso-zero-injection-large-load-ferc/829912/.
Legal and Regulatory Sources
Federal Power Act § 205, 16 U.S.C. § 824d; Federal Power Act § 206, 16 U.S.C. § 824e.
Large Load Interconnection, Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 23, 2025), directed by the Secretary of Energy under 42 U.S.C. § 7173 (Department of Energy Organization Act § 403).
Order Instituting Proceeding Under Section 206 of the Federal Power Act, Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212, Docket No. EL26-70-000 (June 18, 2026).
Order Instituting Proceeding Under Section 206 of the Federal Power Act, PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, Docket No. EL26-67-000 (June 18, 2026).