Advanced Reactor Licensing Paths

The DOE Reactor Pilot Program to NRC Licensing

Executive Summary

The advanced reactor licensing path for 2026 is staged: DOE Reactor Pilot Program authorization for first criticality, then an NRC license under 10 CFR Part 50 or Part 53. Part 50 has produced the permits that exist today: the Kemmerer Unit 1 construction permit on March 4, 2026 and the Clinch River construction permit on September 29, 2026. Part 53 took effect on April 29, 2026 and removes the exemptions that non light water designs needed under Part 50, but the sources reviewed show no completed Part 53 licensing review as of October 10, 2026. The DOE program put four reactors at zero power criticality between June 4 and July 4, 2026, and none of them holds a commercial NRC license.

The right choice depends on what the startup sells. A developer of microreactors under about 20 MWe that plans to build units in volume should start with DOE authorization and follow proposed Part 57, which the NRC issued in April 2026. A developer selling electricity from a single plant before 2030 should file under Part 50 now, the course taken by TerraPower, Kairos Power and the Tennessee Valley Authority. A developer whose design would need many exemptions from Part 50, or one that wants a factory fueled manufactured reactor, should weigh Part 53 against its lack of precedent.

DOE authorization does not authorize commercial deployment. The NRC must still license that deployment under the Atomic Energy Act, and an NRC proposed rule issued April 2, 2026 would amend Parts 50 and 53 so applicants can map DOE or military reviews to NRC requirements while the NRC keeps the final decision.

Detailed Findings

What Does Part 50 Offer an Advanced Reactor Startup in 2026?

Part 50 offers the only path that has delivered construction permits for advanced and small modular reactors in 2026. It is a two step process under 10 CFR Part 50: a construction permit, then an operating license before fuel load. The NRC issued the Kemmerer Unit 1 construction permit to TerraPower on March 4, 2026, after the application arrived in March 2024 and was accepted in May 2024. The plant is a 345 MWe sodium fast reactor paired with molten salt thermal storage that can lift output to 500 MWe for more than five and a half hours.

Kemmerer was the first power reactor application to use a fully risk informed, performance based licensing basis built on the Licensing Modernization Project methodology, documented in NEI 18 04 and endorsed in Regulatory Guide 1.233. It was the fourth non light water reactor to receive a construction permit, after Kairos Power’s Hermes in December 2023, the Abilene Christian University molten salt research reactor in September 2024, and Kairos Power’s Hermes 2 in November 2024. TerraPower must still file a separate Part 50 operating license application, which it plans to do by March 2028.

The Tennessee Valley Authority filed its Clinch River application for a 300 MWe GE Vernova Hitachi BWRX 300 in May 2025. The NRC began its formal review in July 2025, completed the safety evaluation in June 2026, held a public hearing in Oak Ridge, Tennessee in August 2026 under its modernized mandatory hearing process, and issued the permit on September 29, 2026. That is 14 months after the review began and four months ahead of schedule. TVA already held a 2019 early site permit for the site and must still obtain a separate operating license before loading fuel.

The cost of Part 50 for a non light water design is the exemption burden. The NRC states that one goal of Part 53 is to reduce requests for exemptions from Parts 50 and 52, and it acknowledges that the agency can already license non light water reactors under those parts through exemptions. X energy and Dow filed a Part 50 construction permit application in 2025 for four Xe 100 high temperature gas cooled reactors totaling 320 MWe at Seadrift, Texas, and X energy has said that acceptance and review could take up to 30 months.

What Does Part 53 Change for Advanced Reactor Developers?

Part 53 gives developers an optional, technology inclusive alternative to Parts 50 and 52, effective April 29, 2026. The NRC published the final rule at 91 Fed. Reg. 15696 on March 30, 2026, responding to the Nuclear Energy Innovation and Modernization Act of 2019, which directed the agency to create a pathway for optional use by commercial advanced nuclear reactor applicants. The agency finished nearly two years ahead of the statutory deadline of December 31, 2027 and described the rule as its first new initial licensing rule since Part 52 in 1989.

Subpart B sets plant level safety criteria for design basis accidents in section 53.210 and for other licensing basis events in section 53.220, which requires a comprehensive risk metric and risk performance objectives. Section 53.250 requires that no single engineered feature, human action or programmatic control be exclusively relied on for events beyond design basis accidents. The Appendix A general design criteria of Part 50 do not apply; applicants assess failures, hazards and other risk contributors instead. Section 53.090 sets standards for construction permits, operating licenses, early site permits, combined licenses and manufacturing licenses, and the rule adds flexibility for manufactured reactors, including possible factory loading of fuel.

The rule introduces generally licensed reactor operators, who may manipulate controls, including remotely, after meeting training and examination requirements. It offers a performance based physical security option in section 73.100 and a consequence based cyber security option in section 73.110, and an alternative to the Part 100 siting rules that allows higher density sites when societal risks and benefits support them. Part 53 does not incorporate ASME or other codes by reference, so developers can tailor commercial codes to safety significance. Financial qualification may rest on a license condition requiring later proof, while decommissioning financial assurance is largely unchanged.

The NRC’s final regulatory analysis puts net averted costs at $152 million at a 7 percent discount rate and $203 million at a 3 percent rate over 66 years. Those savings are spread across the NRC and all future applicants. The sources reviewed show no developer whose Part 53 application has completed review, and corrections followed the rule on April 13 and July 28, 2026. The NRC issued nine guidance documents with the rule and promised more.

In diligence for deep technology financings, investors ask one question first: which approval does the revenue depend on, and who issues it. A Part 53 applicant answers with a rule less than six months old and no completed review behind it. A Part 50 applicant answers with two permits issued in 2026. On a submarine reactor plant, every procedure traced back to a safety basis that had been accepted before the ship went to sea, and nobody operated against a document the reviewer had not seen. Investors apply the same instinct to a license path.

Where Does Proposed Part 57 Fit for Microreactors?

Proposed 10 CFR Part 57 is the NRC’s attempt to license microreactors and reactors with comparable risk profiles in volume, and it remains a proposal. The NRC issued it on April 24, 2026 with comments due June 15, 2026. Proposed entry criteria are one rem at the exclusion area boundary and a 10 metric ton fuel limit.

Part 57 offers three pathways: a joint construction permit and operating license built on Part 50, a manufacturing license built on 10 CFR 52.167 and expanded to allow centralized manufacturing, fueling and testing with a corresponding Part 70 license for fuel handling, and a standard design approval built on Part 52. The NRC declined to adopt a true general license for multiple reactors, citing sections 11(cc) and 109(a) of the Atomic Energy Act. Advisory Committee on Reactor Safeguards review and adjudicatory hearing opportunities remain.

Initial applications under Part 57 are projected at 6 to 12 months under ideal conditions, and substantial revision is expected before the rule is final. At a July 22, 2026 NRC public meeting, TerraPower said it is weighing both Part 53 and Part 57 for Kemmerer Unit 1 while it plans a Part 50 operating license application by March 2028.

How Does the DOE Reactor Pilot Program Work?

The DOE Reactor Pilot Program lets a company build and test a first of a kind reactor under DOE authorization, outside an NRC license. Executive Order 14301, signed May 23, 2025 and titled Reforming Nuclear Reactor Testing at the Department of Energy, set a goal of three reactors at criticality by July 4, 2026, and DOE named 10 companies in August 2025. In March 2026 DOE extended and expanded the effort into the Nuclear Energy Launch Pad.

A company moves through four milestones: an other transaction agreement with DOE, approval of a nuclear safety design agreement, a preliminary documented safety analysis, and an approved documented safety analysis that enables final authorization and operation. Under the standard path the company keeps design control. Under a strategic partnership project, as with the Oklo Pluto project and Battelle, which manages Idaho National Laboratory, the laboratory contractor keeps design control.

Antares Nuclear reached zero power criticality on June 4, 2026 at Idaho National Laboratory with its Mark 0, a forerunner of its R1 sodium heat pipe cooled, TRISO fueled microreactor. Valar Atomics followed on June 18 at the Utah San Rafael Energy Lab with its 100 kWt Ward 250 helium cooled reactor and reached 10 kWt on June 22. Deployable Energy, a Launch Pad participant, reached criticality on July 1 at Idaho National Laboratory with its Unity microreactor, about 150 days after it began the project. Aalo Atomics reached criticality at 12:20 a.m. Mountain time on July 4 with a zero power test reactor that mirrors the core of its planned 10 MWe sodium cooled Aalo X.

Radiant Industries did not reach criticality by July 4. Its 1 MWe Kaleidos microreactor received preliminary documented safety analysis approval in February 2026 and took its first fuel tranche at the DOME test bed on July 1. Radiant plans a five phase program that ends with a 150 hour full power run without operator intervention, with full power testing slated for later in 2026.

All four criticality events were zero power or very low power tests. Antares plans to test its Mark 1 prototype in 2027, Deployable Energy targets full power and transient testing by July 4, 2027, and Aalo targets a full power test in 2027 and a first commercial multireactor deployment in 2028.

NRC approval is still required before a company can deploy its design commercially, and most pilot and Launch Pad companies target commercial deployment before 2030. The NRC’s proposed rule issued April 2, 2026 would amend 10 CFR Parts 50 and 53 to give applicants an expedited route for designs that DOE or the military reviewed. Applicants must map the earlier work to NRC requirements, 12 NRC staff are embedded with DOE and its pilot projects, and the NRC states it will not rubber stamp another agency’s review. Comments closed on May 4, 2026.

How Do Review Times Compare Across the Three Paths?

Part 50 reviews finished in about one to two years in this cycle, DOE authorization has produced criticality in months, and Part 53 has no measured review time. Kemmerer Unit 1 took about 24 months from submission in March 2024 to the permit on March 4, 2026, which is about 22 months from acceptance and five months ahead of the original August 2026 target. Clinch River took 14 months from the start of formal review, Kairos Power’s Hermes 2 review took just over one year, and NRC staff now estimate about 16,500 hours to finish Clinch River, down from 25,000 hours estimated a year earlier. Executive Order 14300 sets an 18 month ceiling for final decisions on new reactor construction and operation licenses.

International cooperation shortened one review further. The Canadian Nuclear Safety Commission, the NRC and the United Kingdom Office for Nuclear Regulation have a memorandum of cooperation covering small modular reactor work, including joint reviews, and the first two formed a working group on the BWRX 300 in 2022. The review of Ontario Power Generation’s license to construct application took 26 months instead of the typical 32.

Large reactor financing runs on a separate track. DOE announced $17.5 billion in conditional loans on June 23, 2026 so Westinghouse can buy long lead equipment for up to 10 AP1000 reactors, and Westinghouse submitted Revision 20 of the AP1000 design certification document to the NRC in spring 2026. The loan announcement covers AP1000 procurement only, and the sources reviewed describe no comparable DOE loan commitment for an advanced reactor startup.

Which Licensing Path Fits Which Startup?

Match the path to the product. A startup that sells electricity from one plant before 2030 belongs in Part 50. A startup that sells many small identical units belongs on the DOE path now and Part 57 later. A startup whose design would need extensive exemptions belongs in a Part 53 pre application conversation.

The Part 50 case rests on precedent. NRC staff completed construction permit reviews in 2026 for a sodium fast reactor and a boiling water SMR, and the Licensing Modernization Project methodology gives a non light water applicant a documented route through the review. The DOE case rests on speed: Deployable Energy needed about 150 days from project start to criticality. That path produces physics data and a safety analysis, and it does not produce a license to sell power.

The Part 53 case rests on fit. Designs that rely on inherent characteristics for defense in depth, designs sited in higher density areas, and reactors built in a factory and fueled before shipment fit poorly in light water rules. The cost is first mover risk, because the NRC staff has no completed Part 53 review to use as a template.

TerraPower’s sequencing shows how a developer stacks these tools. It held more than 60 preapplication meetings before its 2024 construction permit application, filed under Part 50, and developed 15 topical reports, three technical reports and six white papers. It plans a Part 50 operating license application by March 2028 and is still weighing Parts 53 and 57. TerraPower told the NRC that better prepared staff completed faster reviews, and every path in this report begins with that preparation.

Legal and Regulatory Implications

The Atomic Energy Act places commercial reactor licensing with the NRC, and DOE authorization does not substitute for it. Sections 103 and 104 of the Act, 42 U.S.C. §§ 2133 and 2134, govern commercial and industrial licenses, and section 189a, 42 U.S.C. § 2239, requires a hearing opportunity. The NRC held its Clinch River mandatory hearing in August 2026, and a proposed rule on contested hearings is out for comment under Executive Order 14300.

Section 170 of the Atomic Energy Act, 42 U.S.C. § 2210, supplies the liability protection. Subsection (a) covers NRC licensees through financial protection and indemnification, and subsection (d) covers DOE contractors. A startup that moves from DOE authorization to an NRC license may change which subsection applies, depending on how the DOE project was structured, and its insurance, customer contracts and indemnities must change with it. The sources reviewed do not state the statutory authority for DOE authorization of each pilot project, so counsel should confirm the authority and the site for each.

Executive Order 14300 sets the schedule pressure. It requires fixed deadlines of 18 months for new reactor construction and operation licenses and 12 months for continued operation of existing plants, directs a wholesale rewrite of NRC regulations within 18 months, directs that Advisory Committee on Reactor Safeguards reviews be limited to matters that are truly novel or noteworthy, and ties fee recovery to the deadlines. The NRC chair has said some EO rulemakings will miss the 18 month target, and the NRC planned a new Office of Advanced Reactors for mid June 2026.

Environmental review remains part of every NRC path under 10 CFR Part 51, with the executive order pushing the NRC toward environmental assessments and findings of no significant impact where it can. Part 53 also changed conforming rules: Part 26 gained a new subpart M on fitness for duty, Part 50 changed in section 50.160 and Appendices B and E, and Part 73 gained sections 73.100, 73.110 and 73.120. Applicants should track the correcting amendments published July 28, 2026.

Want more industry insights? I publish daily analysis on the intersection of deep tech and venture law.

Subscribe to The Innovation Attorney on Substack

Open Questions

No Part 53 application has completed review, so no one can say whether staff will beat the 14 months achieved at Clinch River. Investors pricing schedule risk need the first docketed Part 53 application and its acceptance review schedule.

Whether the final Part 57 rule keeps the one rem exclusion area boundary and 10 metric ton fuel limit determines which microreactors qualify. Comments closed June 15, 2026, and the final text will show how many designs fall outside it.

The final rule amending Parts 50 and 53 will show how much of a DOE safety analysis the NRC accepts. A zero power criticality test is a short evidence record, and applicants need to know whether the NRC will treat it as a starting point or a full demonstration.

Radiant’s 150 hour full power run, planned for later in 2026, will show whether a DOE authorized microreactor can generate operating data in a form the NRC will use.

The liability transition from DOE authorization to an NRC license under 42 U.S.C. § 2210 has no published playbook in the sources reviewed, and each startup’s insurers and customers will ask for one.

NRC staff capacity matters for every path. The executive order demands 18 month decisions while directing reorganization and reductions in force, and the NRC chair has acknowledged that some rulemakings will run late.

The next report in this series examines proposed Part 57 section by section and tests whether a startup could ship 50 microreactors a year under the NRC’s manufacturing license pathway.

Source List

Primary Nuclear and Legal Sources

Risk Informed, Technology Inclusive Regulatory Framework for Advanced Reactors, 91 Fed. Reg. 15696 (Mar. 30, 2026) (final rule, 10 C.F.R. pt. 53, effective Apr. 29, 2026). https://www.federalregister.gov/documents/2026/03/30/2026-06048/risk-informed-technology-inclusive-regulatory-framework-for-advanced-reactors Primary text of the Part 53 final rule, with the section numbers, effective date and regulatory analysis figures cited above.

U.S. Nuclear Regulatory Commission, News Release No. 26 079, NRC Approves Construction Permit for TVA’s Clinch River Small Modular Reactor (Sept. 29, 2026). https://www.nrc.gov/about-nrc/news-releases/2026/26-079 Agency announcement of the Clinch River construction permit, the 14 month review and the August 2026 hearing.

U.S. Nuclear Regulatory Commission, News Release No. 26 035, NRC Issues Part 53 (Mar. 25, 2026). https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-035.pdf Agency announcement of the Part 53 final rule, the nine guidance documents and the comparison to Parts 50 and 52.

Exec. Order No. 14300, Ordering the Reform of the Nuclear Regulatory Commission (May 23, 2025). https://www.whitehouse.gov/presidential-actions/2025/05/ordering-the-reform-of-the-nuclear-regulatory-commission/ Source of the 18 month and 12 month licensing deadlines and the directive to rewrite NRC regulations.

Exec. Order No. 14301, Reforming Nuclear Reactor Testing at the Department of Energy (May 23, 2025), as described in the American Nuclear Society report of July 2, 2026 listed below. Creates the Reactor Pilot Program and sets the three reactors by July 4, 2026 goal.

Atomic Energy Act of 1954 §§ 103, 104, 170 and 189, 42 U.S.C. §§ 2133, 2134, 2210 and 2239. Statutory basis for commercial reactor licensing, liability protection and hearing rights.

Nuclear Energy Innovation and Modernization Act of 2019, 42 U.S.C. § 2215 note. Directed the NRC to create the optional pathway that became Part 53.

10 C.F.R. pts. 50, 51, 52, 53, 70, 73 and 100 (2026), and proposed 10 C.F.R. pt. 57 (2026). The NRC regulations that define the construction permit, operating license, environmental, security and siting requirements discussed above.

U.S. Department of Energy, Department of Energy Announces American Nuclear Supply Chain Loans (June 23, 2026). https://www.energy.gov/articles/department-energy-announces-american-nuclear-supply-chain-loans DOE announcement of the $17.5 billion conditional loan commitment for AP1000 long lead equipment.

Secondary Nuclear Sources

American Nuclear Society, Nuclear Newswire, Developers, Officials Talk Advanced Reactor Outlook with NRC (July 22, 2026). https://www.ans.org/news/2026-07-22/article-8237/developers-officials-talk-advanced-reactor-outlook-with-nrc/ Report of the July 22, 2026 NRC public meeting: TerraPower plans, the CNSC and NRC BWRX 300 review, the pilot program criticality events, Radiant, AP1000 Revision 20 and the DOE loans.

American Nuclear Society, Nuclear Newswire, The Deadline Arrives: Checking in on the Reactor Pilot Program (July 2, 2026). https://www.ans.org/news/article-8178/the-deadline-arrives-checking-in-on-the-reactor-pilot-program/ Describes the four authorization milestones, the program history and company by company status.

American Nuclear Society, Nuclear Newswire, Aalo Atomics Achieves Criticality on July 4 (July 6, 2026). https://www.ans.org/news/article-8182/aalo-atomics-achieves-criticality-on-july-4/ Source for the time, place and design of the Aalo criticality event.

American Nuclear Society, Nuclear Newswire, NRC Approves TerraPower Construction Permit (Mar. 4, 2026). https://www.ans.org/news/article-7818/nrc-approves-terrapower-construction-permit/ Source for the Kemmerer Unit 1 permit date, review timeline, design and licensing basis.

American Nuclear Society, Nuclear Newswire, Clinch River Construction Permit Recommendation Follows Safety Evaluation (July 1, 2026). https://www.ans.org/news/article-8174/clinch-river-construction-permit-recommendation-follows-safety-evaluation/ Source for the Clinch River safety evaluation and the staff hours estimate.

American Nuclear Society, Nuclear Newswire, NRC Proposed Rule for Licensing Reactors Authorized by DOE, DOD (Apr. 6, 2026). https://www.ans.org/news/article-7912/nrc-proposed-rule-for-licensing-reactors-authorized-by-doe-dod/ Source for the proposed amendments to Parts 50 and 53 that credit DOE and military reviews.

American Nuclear Society, Nuclear Newswire, DOE Announces $17.5B in Conditional Loans for AP1000 Builds (June 23, 2026). https://www.ans.org/news/2026-06-23/article-8142/doe-announces-175b-in-conditional-loans-for-ap1000-builds/ Details of the loan recipients, structure and AP1000 scope.

World Nuclear News, First Construction Permit Issued for BWRX 300 SMR in US (Sept. 30, 2026). https://world-nuclear-news.org/articles/first-construction-permit-issued-for-bwrx300-smr-in-us Independent report of the Clinch River permit, application date and review milestones.

Kairos Power, Nuclear Regulatory Commission Approves Construction Permits for Hermes 2 Demonstration Plant (Nov. 20, 2024). https://www.kairospower.com/updates/nuclear-regulatory-commission-approves-construction-permits-for-hermes-2-demonstration-plant Developer statement on the Hermes 2 permits, the Part 50 two step process and the Hermes permit of December 2023.

POWER Magazine, How EO 14300 Is Reshaping NRC Nuclear Licensing and Regulation (2026) (headline shortened). https://www.powermag.com/how-trumps-eo-14300-is-reshaping-nrc-nuclear-licensing-and-regulation/ Source for the status of EO 14300 rulemakings and the proposed Part 57 entry criteria.

Secondary Legal Sources

POWER Magazine, Dow and X energy Advance Landmark Nuclear Project in Texas with Construction Permit Filing (Apr. 3, 2025). https://www.powermag.com/dow-and-x-energy-advance-landmark-nuclear-project-in-texas-with-construction-permit-filing Source for the Long Mott Part 50 application and the 30 month review estimate.

Orrick, Herrington and Sutcliffe LLP, NRC Proposes New Framework to Enable High Volume Microreactor Deployment (May 2026). https://www.orrick.com/en/Insights/2026/05/NRC-Proposes-New-Framework-to-Enable-High-Volume-Microreactor-Deployment Practitioner analysis of proposed Part 57, its three pathways and the NRC’s treatment of general licensing.

Bibliography

American Nuclear Society. “Developers, Officials Talk Advanced Reactor Outlook with NRC.” Nuclear Newswire, July 22, 2026. https://www.ans.org/news/2026-07-22/article-8237/developers-officials-talk-advanced-reactor-outlook-with-nrc/.

American Nuclear Society. “The Deadline Arrives: Checking in on the Reactor Pilot Program.” Nuclear Newswire, July 2, 2026. https://www.ans.org/news/article-8178/the-deadline-arrives-checking-in-on-the-reactor-pilot-program/.

American Nuclear Society. “Aalo Atomics Achieves Criticality on July 4.” Nuclear Newswire, July 6, 2026. https://www.ans.org/news/article-8182/aalo-atomics-achieves-criticality-on-july-4/.

American Nuclear Society. “NRC Approves TerraPower Construction Permit.” Nuclear Newswire, March 4, 2026. https://www.ans.org/news/article-7818/nrc-approves-terrapower-construction-permit/.

American Nuclear Society. “Clinch River Construction Permit Recommendation Follows Safety Evaluation.” Nuclear Newswire, July 1, 2026. https://www.ans.org/news/article-8174/clinch-river-construction-permit-recommendation-follows-safety-evaluation/.

American Nuclear Society. “NRC Proposed Rule for Licensing Reactors Authorized by DOE, DOD.” Nuclear Newswire, April 6, 2026. https://www.ans.org/news/article-7912/nrc-proposed-rule-for-licensing-reactors-authorized-by-doe-dod/.

American Nuclear Society. “DOE Announces $17.5B in Conditional Loans for AP1000 Builds.” Nuclear Newswire, June 23, 2026. https://www.ans.org/news/2026-06-23/article-8142/doe-announces-175b-in-conditional-loans-for-ap1000-builds/.

Atomic Energy Act of 1954 §§ 103, 104, 170, 189, 42 U.S.C. §§ 2133, 2134, 2210, 2239.

10 C.F.R. pts. 50, 51, 52, 53, 70, 73, 100 (2026); proposed 10 C.F.R. pt. 57 (2026).

Exec. Order No. 14300, Ordering the Reform of the Nuclear Regulatory Commission (May 23, 2025). https://www.whitehouse.gov/presidential-actions/2025/05/ordering-the-reform-of-the-nuclear-regulatory-commission/.

Exec. Order No. 14301, Reforming Nuclear Reactor Testing at the Department of Energy (May 23, 2025).

Kairos Power. “Nuclear Regulatory Commission Approves Construction Permits for Hermes 2 Demonstration Plant.” November 20, 2024. https://www.kairospower.com/updates/nuclear-regulatory-commission-approves-construction-permits-for-hermes-2-demonstration-plant.

Morgan, Lewis and Bockius LLP. “NRC Launches Fresh Licensing Framework for New Reactors.” April 2026. https://www.morganlewis.com/pubs/2026/04/nrc-launches-fresh-licensing-framework-for-new-reactors.

Nuclear Energy Innovation and Modernization Act of 2019, 42 U.S.C. § 2215 note.

Nuclear Regulatory Commission. Risk Informed, Technology Inclusive Regulatory Framework for Advanced Reactors. 91 Fed. Reg. 15696 (Mar. 30, 2026) (to be codified at 10 C.F.R. pt. 53). https://www.federalregister.gov/documents/2026/03/30/2026-06048/risk-informed-technology-inclusive-regulatory-framework-for-advanced-reactors.

Nuclear Regulatory Commission. News Release No. 26 079, NRC Approves Construction Permit for TVA’s Clinch River Small Modular Reactor. Sept. 29, 2026. https://www.nrc.gov/about-nrc/news-releases/2026/26-079.

Nuclear Regulatory Commission. News Release No. 26 035, NRC Issues Part 53. Mar. 25, 2026. https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-035.pdf.

Orrick, Herrington and Sutcliffe LLP. “NRC Proposes New Framework to Enable High Volume Microreactor Deployment.” May 2026. https://www.orrick.com/en/Insights/2026/05/NRC-Proposes-New-Framework-to-Enable-High-Volume-Microreactor-Deployment.

POWER Magazine. “How EO 14300 Is Reshaping NRC Nuclear Licensing and Regulation” (headline shortened). 2026. https://www.powermag.com/how-trumps-eo-14300-is-reshaping-nrc-nuclear-licensing-and-regulation/.

POWER Magazine. “Dow and X energy Advance Landmark Nuclear Project in Texas with Construction Permit Filing.” April 3, 2025. https://www.powermag.com/dow-and-x-energy-advance-landmark-nuclear-project-in-texas-with-construction-permit-filing.

U.S. Department of Energy. Department of Energy Announces American Nuclear Supply Chain Loans. June 23, 2026. https://www.energy.gov/articles/department-energy-announces-american-nuclear-supply-chain-loans.

World Nuclear News. “First Construction Permit Issued for BWRX 300 SMR in US.” September 30, 2026. https://world-nuclear-news.org/articles/first-construction-permit-issued-for-bwrx300-smr-in-us.

Interested in analysis about the intersection of tech, policy and the law? Check out my Substack channel. https://theinnovationattorney.substack.com/